186 Prague St
San Francisco permit 202207017657 · Excelsior
427 sf. conversion of (e) grd flr to living area w/ (n) laundry room & storage, fmy rm, enlarged bath-2, bedrm-3 & service hall. 244 sf. remodel of (e) grd flr living area. relocate fau & water heater. structural framing work related to remodel. replace rear yard facing windows/doors/patio door.
- Filed
- Jul 1, 2022
- Issued
- Jun 15, 2023 (11 months after filing)
- Completed
- Feb 16, 2024 (8 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 16 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 1, 2022 | Jul 7, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2022 | Jan 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 7, 2022 | Jun 2, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 9, 2023 | May 16, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2023 | Mar 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2023 | Feb 3, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 22, 2023 | Feb 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2023 | Mar 7, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 3, 2023 | Mar 6, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 6, 2023 | Mar 7, 2023 | — |
Building plan review Building Inspection · BLDG | May 16, 2023 | May 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2023 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2023 | Jun 2, 2023 | — |
Zoning review Planning · CP-ZOC | May 16, 2023 | May 19, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2023 | May 23, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 2, 2023 | Jun 15, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $200,000
| Name | Role | License on permit |
|---|---|---|
| Andy A Fiammengo | Engineer | C65927 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025