107 Hahn St
San Francisco permit 202207067863 · Visitacion Valley
Legalize horizontal add & 2nd unit. build out new separate entrance. relocate bath, add egress window for gnd fl unit. no remodeling on 2nd fl except for new ext stair from (e) roof 262to rear c
- Filed
- Jul 6, 2022
- Issued
- Jun 1, 2023 (11 months after filing)
- Completed
- Sep 17, 2024 (16 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 29 stops across 5 departments
- Comments issued
- Once, by Public Works
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Building inspector Building Inspection · BID-INSP | Jul 6, 2022 | Jul 6, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 6, 2022 | Jul 7, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2022 | Jan 10, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Oct 31, 2022 | Jan 10, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 11, 2023 | Mar 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 11, 2023 | Jan 18, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 14, 2023 | Feb 16, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 17, 2023 | Mar 2, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 13, 2023 | Mar 13, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 13, 2023 | Mar 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2023 | Apr 5, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 27, 2023 | May 9, 2023 | — |
Development fee collection Building Inspection · DFCU | May 12, 2023 | May 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2023 | May 16, 2023 | — |
Urban forestry Public Works · DPW-BUF | May 12, 2023 | May 12, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 16, 2023 | May 23, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 23, 2023 | Jun 1, 2023 | — |
Building inspector Building Inspection · BID-INSP | May 24, 2023 | May 24, 2023 | — |
Addendum 1: Arch / structural / t-24 / final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 7, 2023 | Jun 7, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 7, 2023 | Nov 8, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 21, 2023 | Aug 8, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 9, 2023 | Aug 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2023 | Aug 31, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 31, 2023 | Nov 6, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2023 | Oct 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 8, 2023 | Nov 14, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 14, 2023 | Nov 16, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Nov 17, 2023 | Nov 17, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 17, 2023 | Nov 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $262,000
| Name | Role | License on permit |
|---|---|---|
| Alan Kiyoshi Toma Design Studio | Architect | C20518 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025