347 Los Palmos Dr
San Francisco permit 202207077948 · West of Twin Peaks
Add 3rd floor with bath, expand and remodel 2nd floor with new rear deck and stair, convert unconditioned space to habitable on 1st floor with new half bath.
- Filed
- Jul 7, 2022
- Issued
- Jul 15, 2024 (24 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 58 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Fire Department
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 7, 2022 | Jul 8, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 8, 2022 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 8, 2022 | Jul 11, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Jan 24, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2023 | May 9, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 29, 2023 | May 22, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 29, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2023 | Apr 21, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 4, 2024 | Jun 10, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 4, 2024 | Jun 10, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 4, 2024 | Jun 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 4, 2024 | Jun 5, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 4, 2024 | Jun 10, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 18, 2024 | Jun 18, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Jun 18, 2024 | Jun 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 18, 2024 | Jun 25, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jun 18, 2024 | Jun 24, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 20, 2024 | Jun 21, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 20, 2024 | Jul 11, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 20, 2024 | Jun 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jun 21, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 3, 2024 | Jul 3, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jul 3, 2024 | Jul 8, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Jul 11, 2024 | Jul 15, 2024 | Administrative |
Addendum 1: Final.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 31, 2024 | Aug 9, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2024 | Aug 12, 2024 | Administrative |
Electrical pre-screening Building Inspection · PRE-MECH-E | Aug 5, 2024 | Aug 5, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Aug 8, 2024 | Aug 8, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Aug 9, 2024 | Aug 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 12, 2024 | Sep 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 12, 2024 | Sep 3, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 12, 2024 | Sep 9, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 12, 2024 | Aug 12, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 12, 2024 | Aug 12, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Aug 12, 2024 | Apr 21, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 18, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 12, 2024 | Nov 19, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Nov 12, 2024 | Nov 14, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 12, 2024 | Nov 14, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 12, 2024 | Dec 9, 2024 | Approved |
Building plan review Building Inspection · BLDG | Nov 22, 2024 | Jan 24, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 22, 2024 | Nov 27, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Nov 22, 2024 | Dec 11, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 22, 2024 | Nov 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 2, 2024 | Dec 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 2, 2024 | Dec 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2025 | Jan 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Jan 24, 2025 | Jan 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2025 | Jan 27, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2025 | Feb 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | Feb 11, 2025 | Feb 18, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 11, 2025 | Feb 12, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 11, 2025 | Feb 26, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 11, 2025 | Feb 12, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 11, 2025 | Feb 25, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Mar 7, 2025 | Apr 14, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 15, 2025 | May 15, 2025 | Administrative |
Zoning review Planning · CP-ZOC | Apr 18, 2025 | Apr 21, 2025 | Approved |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $280,000
| Name | Role | License on permit |
|---|---|---|
| Geoffrey S Gainer Actual-Size Architecture | Architect | C27762 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025