San Francisco permit 202207077948 · West of Twin Peaks

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 347 Los Palmos Dr, Mar 2025
Scope of work
As written on the permit application.

Add 3rd floor with bath, expand and remodel 2nd floor with new rear deck and stair, convert unconditioned space to habitable on 1st floor with new half bath.

Timeline
Key dates from the city record.
Filed
Jul 7, 2022
Issued
Jul 15, 2024 (24 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
58 stops across 6 departments
Comments issued
10 times, by Building Inspection, Fire Department
Put on hold
5 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 8, 2022—

Zoning review

Planning · CP-ZOC

Jan 23, 2023—

Permit Processing Center

Building Inspection · PPC

Jul 11, 2024Administrative

Planning neighborhood notice

Planning · CP-NP

Mar 28, 2023—

Building plan review

Building Inspection · BLDG

May 9, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

May 22, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 5, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 21, 2023—

Building plan review

Building Inspection · BLDG

Jun 10, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 10, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jun 4, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 5, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jun 10, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 18, 2024Issued Comments

Zoning review

Planning · CP-ZOC

Jun 18, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 25, 2024Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Jun 24, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 21, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 11, 2024Approved

Zoning review

Planning · CP-ZOC

Jun 21, 2024Approved

Building plan review

Building Inspection · BLDG

Jun 21, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 3, 2024Approved-Stipulated

Urban forestry

Public Works · DPW-BUF

Jul 8, 2024Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Jul 15, 2024Administrative

Addendum 1: Final.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Aug 9, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2024Administrative

Electrical pre-screening

Building Inspection · PRE-MECH-E

Aug 5, 2024Not Applicable

Mechanical pre-screening

Building Inspection · PRE-MECH

Aug 8, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Aug 9, 2024Approved

Building plan review

Building Inspection · BLDG

Sep 19, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 3, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Sep 9, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 12, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Aug 12, 2024Approved

Permit Processing Center

Building Inspection · PPC

Apr 21, 2025Administrative

Building plan review

Building Inspection · BLDG

Nov 18, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Nov 19, 2024Approved

Fire prevention review

Fire Department · SFFD

Nov 14, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 14, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 9, 2024Approved

Building plan review

Building Inspection · BLDG

Jan 24, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Nov 27, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Dec 11, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 27, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 6, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 4, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jan 27, 2025Approved

Fire prevention review

Fire Department · SFFD

Jan 27, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jan 27, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 6, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 18, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 12, 2025Approved

Fire prevention review

Fire Department · SFFD

Feb 26, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Feb 12, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 25, 2025Approved

Urban forestry

Public Works · DPW-BUF

Apr 14, 2025Approved

Central Permit Bureau

Building Inspection · CPB

May 15, 2025Administrative

Zoning review

Planning · CP-ZOC

Apr 21, 2025Approved

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$280,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Geoffrey S Gainer

Actual-Size Architecture

ArchitectC27762
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202207077948 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record