1027 Felton St
San Francisco permit 202207118208 · Portola
Addition to back side of single family residence to include new bedrooms with 2nd floor deck above. remodel at 1st floor to include media room and bathrooms.
- Filed
- Jul 11, 2022
- Issued
- Aug 15, 2023 (13 months after filing)
- Completed
- Dec 13, 2023 (4 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 18 stops across 4 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 11, 2022 | Jul 18, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 12, 2022 | Aug 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 18, 2022 | Apr 6, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Jan 26, 2023 | Apr 7, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 6, 2023 | Apr 6, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2023 | Jun 22, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Apr 7, 2023 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2023 | May 10, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2023 | Apr 12, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 21, 2023 | Jul 19, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 21, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 21, 2023 | Aug 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 21, 2023 | Jun 30, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 19, 2023 | Jul 26, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2023 | Jul 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2023 | Aug 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2023 | Jul 26, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Aug 8, 2023 | Aug 15, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $95,000
| Name | Role | License on permit |
|---|---|---|
| Ryan G Morris Morris Architecture | Architect | C33359 |
| Robert Hugh Shaffer Morris Shaffer Engineering | Engineer | C45322 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019