San Francisco permit 202207118208 · Portola

AdditionFull plan reviewComplete
Street view · Apr 2019
Google Street View of 1027 Felton St, Apr 2019
Scope of work
As written on the permit application.

Addition to back side of single family residence to include new bedrooms with 2nd floor deck above. remodel at 1st floor to include media room and bathrooms.

Timeline
Key dates from the city record.
Filed
Jul 11, 2022
Issued
Aug 15, 2023 (13 months after filing)
Completed
Dec 13, 2023 (4 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
18 stops across 4 departments
Comments issued
None
Put on hold
4 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jul 18, 2022—

Permit Processing Center

Building Inspection · PPC

Aug 8, 2023—

Zoning review

Planning · CP-ZOC

Apr 6, 2023—

Planning neighborhood notice

Planning · CP-NP

Apr 7, 2023—

Zoning review

Planning · CP-ZOC

Apr 6, 2023—

Building plan review

Building Inspection · BLDG

Jun 22, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 21, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 10, 2023—

Street use and mapping

Public Works · DPW-BSM

Apr 12, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 19, 2023—

Zoning review

Planning · CP-ZOC

Jun 22, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 8, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 30, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 26, 2023—

Zoning review

Planning · CP-ZOC

Jul 20, 2023—

Building plan review

Building Inspection · BLDG

Aug 8, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 26, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 15, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$95,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Ryan G Morris

Morris Architecture

ArchitectC33359
Robert Hugh Shaffer

Morris Shaffer Engineering

EngineerC45322
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202207118208 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record