1100 Prague St
San Francisco permit 202207128226 · Excelsior
To comply with nov# 202055379. (n) adu at ground level.
- Filed
- Jul 12, 2022
- Issued
- May 25, 2023 (10 months after filing)
- Completed
- Sep 12, 2024 (16 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 23 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | May 31, 2022 | May 31, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Jul 12, 2022 | Jul 12, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 12, 2022 | Mar 13, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 12, 2022 | Mar 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2022 | Mar 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2022 | Jul 14, 2022 | — |
Urban forestry Public Works · DPW-BUF | Jul 12, 2022 | May 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2022 | Jul 15, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 12, 2022 | May 8, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 6, 2023 | Mar 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 6, 2023 | Apr 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 6, 2023 | Mar 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 9, 2023 | Mar 9, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 22, 2023 | Mar 22, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 13, 2023 | Apr 20, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 13, 2023 | Apr 14, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2023 | Apr 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 13, 2023 | Apr 14, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 17, 2023 | Apr 18, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 17, 2023 | Apr 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 17, 2023 | Apr 19, 2023 | — |
Development fee collection Building Inspection · DFCU | May 8, 2023 | May 8, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 8, 2023 | May 25, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $162,826
| Name | Role | License on permit |
|---|---|---|
| Bishwendu Kumar Paul Earthquake & Structural | Engineer | S3093 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025