88 Castenada Av
San Francisco permit 202207138338 · West of Twin Peaks
Renovation & vertical expansion. alteration to interior comprises of reconfiguration of interior stair. modification of ground fl and l2 floor plans & windows. exterior modifications include front & rear facades, exterior entry area landscaping, and addition of stair penthouse.
- Filed
- Jul 13, 2022
- Issued
- May 10, 2024 (22 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 33 stops across 4 departments
- Comments issued
- 5 times, by Building Inspection
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 13, 2022 | Jul 27, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 27, 2022 | Jun 8, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 27, 2022 | Feb 26, 2024 | — |
Planning neighborhood notice Planning · CP-NP | Apr 4, 2023 | Jun 8, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 8, 2023 | Jul 27, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jun 8, 2023 | Oct 11, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2023 | Sep 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 8, 2023 | Jun 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 8, 2023 | Jul 5, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 26, 2023 | Oct 11, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 26, 2023 | Sep 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 26, 2023 | Sep 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 26, 2023 | Sep 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2023 | Sep 27, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2023 | Nov 3, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 5, 2023 | Dec 8, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Dec 20, 2023 | Jan 31, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 20, 2023 | Dec 20, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 20, 2023 | Dec 27, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 20, 2023 | Jan 5, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 20, 2023 | Dec 21, 2023 | Approved |
Zoning review Planning · CP-ZOC | Feb 1, 2024 | Feb 1, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 1, 2024 | Feb 15, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 1, 2024 | Feb 15, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 1, 2024 | Feb 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2024 | Feb 21, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2024 | Feb 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Feb 22, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 22, 2024 | Feb 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Feb 22, 2024 | Feb 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Feb 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 26, 2024 | May 10, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,040,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Blau Spiegel Saw//Spiegel Ahara Workshop | Architect | C34488 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Nov 2017