Scope of work
As written on the permit application.

Convert (e) 1fl storage to adu.comply with nov 202185655.

Timeline
Key dates from the city record.
Filed
Jul 19, 2022
Issued
Jan 26, 2024 (18 months after filing)
Completed
Nov 13, 2025 (22 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
36 stops across 5 departments
Comments issued
4 times, by Fire Department, Building Inspection
Put on hold
11 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 1, 2022—

Electrical inspector

Building Inspection · EID-INSP

Jul 20, 2022—

Building inspector

Building Inspection · BID-INSP

Jul 22, 2022—

Permit Processing Center

Building Inspection · PPC

Jan 19, 2024Administrative

Zoning review

Planning · CP-ZOC

Jul 21, 2023—

Building plan review

Building Inspection · BLDG

Jun 9, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jun 12, 2023—

Fire prevention review

Fire Department · SFFD

Jun 27, 2023—

Street use and mapping

Public Works · DPW-BSM

Aug 9, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Aug 5, 2022—

Structural plan approval

Building Inspection · PAD-STR

Jun 8, 2023—

Zoning review

Planning · CP-ZOC

Jan 4, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 18, 2023—

Building plan review

Building Inspection · BLDG

Jul 18, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 13, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 12, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 20, 2023—

Fire prevention review

Fire Department · SFFD

Sep 26, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Jul 18, 2023Administrative

Building plan review

Building Inspection · BLDG

Jul 25, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 21, 2023—

Street use and mapping

Public Works · DPW-BSM

Jul 20, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 19, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 20, 2023—

Building plan review

Building Inspection · BLDG

Sep 21, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Sep 25, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 19, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Dec 15, 2023Approved

Fire prevention review

Fire Department · SFFD

Jan 2, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Dec 6, 2023Approved

Zoning review

Planning · CP-ZOC

Dec 7, 2023Approved

Structural plan approval

Building Inspection · PAD-STR

Dec 20, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 12, 2023Approved

Building plan review

Building Inspection · BLDG

Dec 19, 2023Approved

Development fee collection

Building Inspection · DFCU

Jan 5, 2024Administrative

Central Permit Bureau

Building Inspection · CPB

Jan 26, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$189,542
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Don GeeEngineerC21547
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202207198815 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record