4160 20th St
San Francisco permit 202207208951 · Castro/Upper Market
To comply with nov# 202293305. partial conversion of existing basement level into 530 sf adu unit.
- Filed
- Jul 20, 2022
- Issued
- Jun 8, 2023 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 29 stops across 5 departments
- Comments issued
- None
- Put on hold
- 7 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 18, 2022 | Aug 4, 2022 | — |
Apartment and hotel inspection Building Inspection · HIS | Jul 20, 2022 | Jul 20, 2022 | — |
Building inspector Building Inspection · BID-INSP | Aug 3, 2022 | Aug 3, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 4, 2022 | May 25, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 5, 2022 | Oct 20, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 5, 2022 | Jan 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 5, 2022 | Sep 27, 2022 | — |
Urban forestry Public Works · DPW-BUF | Aug 5, 2022 | Mar 9, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Aug 5, 2022 | Sep 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 5, 2022 | Aug 8, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 4, 2022 | Oct 4, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 20, 2022 | Nov 29, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 30, 2022 | Nov 30, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Dec 5, 2022 | Dec 5, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 12, 2023 | Jan 12, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 9, 2023 | May 25, 2023 | — |
Development fee collection Building Inspection · DFCU | May 25, 2023 | May 25, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 25, 2023 | Jun 8, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jun 16, 2023 | Jun 16, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 16, 2023 | Aug 28, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 16, 2023 | Sep 1, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jun 16, 2023 | Jun 20, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2023 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jun 28, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jun 16, 2023 | Sep 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Aug 30, 2023 | Aug 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 30, 2023 | Sep 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 30, 2023 | Sep 1, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 15, 2023 | Sep 25, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Mahya Salehi Fadardi | Architect | C38610 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2016