4007 25th St
San Francisco permit 202207269345 · Noe Valley
Extend rear of house 3';1st fl - add (n) family room with bath & laundry @ rear of garage; add a (n) exit passage way & stair from the right of way to the rear yard to provide ladder access & emergency exiting to comply w/eg-02; 2nd fl - add powder room, renovate kitchen, and add new stair from kitc
- Filed
- Jul 26, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 16 stops across 4 departments
- Comments issued
- None
- Put on hold
- 4 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 26, 2022 | Aug 9, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 8, 2022 | Apr 27, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Mar 7, 2023 | Dec 8, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 28, 2023 | Nov 17, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Apr 28, 2023 | Jul 27, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 10, 2023 | Jul 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 13, 2023 | Aug 15, 2023 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 27, 2023 | Aug 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Sep 18, 2023 | Sep 18, 2023 | Approved-Stipulated |
Structural plan approval Building Inspection · PAD-STR | Nov 17, 2023 | Nov 21, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 21, 2023 | Nov 27, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Nov 29, 2023 | Dec 1, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 1, 2023 | Dec 8, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 11, 2023 | Dec 12, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 13, 2023 | Dec 13, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2023 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Approved
- Estimated cost
- $400,000
| Name | Role | License on permit |
|---|---|---|
| Lev H Weisbach Weishbach Architecture | Architect | C22099 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2022