1701 Jerrold Av
San Francisco permit 202207289441 · Bayview Hunters Point
Att modification unmanned telecom facility: replace 6 antennas, remove 9 rrus, 6 new rrus, 6 diplexers, new rf safety signs striping rooftop. 1 6648 baseband unit max in e rack
- Filed
- Jul 28, 2022
- Issued
- Nov 28, 2022 (4 months after filing)
- Completed
- Dec 1, 2022 (within 1 month of issuance)
- Review stops
- 10 stops across 5 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Jul 28, 2022 | Jul 28, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jul 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Jul 28, 2022 | Jul 28, 2022 | — |
Public health review Public Health · HEALTH | Jul 28, 2022 | Jul 28, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Aug 1, 2022 | Aug 1, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 1, 2022 | Aug 1, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2022 | Aug 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 1, 2022 | Aug 1, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 28, 2022 | Nov 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Nov 28, 2022 | Nov 28, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $45,000
| Name | Role | License on permit |
|---|---|---|
| Zahra Gerami | Architect | 89570 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026