1080 Hampshire St
San Francisco permit 202207289445 · Mission
Add 1 unit at gr fl zoning rh2,add 29 sf under 2nd fl overhang at rear, remodel 2nd fl unit. correct deck and stair rear violation 202183612
- Filed
- May 31, 2024
- Issued
- Feb 18, 2025 (9 months after filing)
- Completed
- Mar 17, 2026 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2024 typically took 6 months to be issued (median of 422 issued permits).
- Review stops
- 28 stops across 6 departments
- Comments issued
- 7 times, by Planning, Building Inspection, Public Utilities
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Jul 28, 2022 | Jul 28, 2022 | Approved |
Intake Building Inspection · INTAKE | Jul 28, 2022 | Jul 28, 2022 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2022 | Jun 3, 2024 | Issued Comments |
Intake Building Inspection · INTAKE | May 9, 2024 | May 9, 2024 | Administrative |
Zoning review Planning · CP-ZOC | May 9, 2024 | May 9, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | May 14, 2024 | May 14, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | May 19, 2024 | May 29, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2024 | May 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 29, 2024 | May 29, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 3, 2024 | Jun 3, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jun 3, 2024 | Jun 17, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2024 | Jun 10, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 3, 2024 | Jun 7, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 3, 2024 | Jun 4, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jun 3, 2024 | Jun 3, 2024 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Jun 3, 2024 | Jan 23, 2025 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jun 17, 2024 | Jun 25, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2024 | Jun 25, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2024 | Aug 16, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 20, 2024 | Sep 16, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 20, 2024 | Aug 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 20, 2024 | Aug 20, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 23, 2024 | Aug 23, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 18, 2024 | Sep 19, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 7, 2024 | Oct 7, 2024 | Approved |
Zoning review Planning · CP-ZOC | Dec 23, 2024 | Dec 23, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jan 17, 2025 | Jan 23, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2025 | Feb 18, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $543,000
| Name | Role | License on permit |
|---|---|---|
| Samuel Kwong Arcus Architecture | Architect | C14679 |
| Hongbo Yang W.H. Consultant Inc. | Engineer | C-88467 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025