11 Frida Kahlo Wy
San Francisco permit 202207289451 · West of Twin Peaks
Bldg e - mayor's ed# 17-02. erect a 7-story, type 3a over type 1a construction, with 128 residential units & community facility.
- Filed
- Jul 28, 2022
- Issued
- Jan 8, 2025 (29 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 111 stops across 8 departments
- Comments issued
- 25 times, by Building Inspection, Public Works, Public Health, Fire Department, Public Utilities
- Put on hold
- 6 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 28, 2022 | Jul 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Jul 28, 2022 | Feb 13, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 29, 2022 | Aug 23, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Aug 24, 2022 | Nov 21, 2022 | — |
Building plan review Building Inspection · BLDG | Aug 24, 2022 | Dec 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Aug 24, 2022 | Jan 3, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2022 | Jan 27, 2025 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2022 | Sep 15, 2022 | — |
Public health review Public Health · HEALTH | Aug 24, 2022 | Sep 30, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 7, 2022 | Feb 10, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2022 | Nov 8, 2022 | — |
Public health review Public Health · HEALTH | Nov 7, 2022 | Nov 9, 2022 | — |
Building plan review Building Inspection · BLDG | Dec 15, 2022 | Dec 29, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Dec 16, 2022 | Dec 23, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 16, 2022 | Dec 20, 2022 | — |
Public health review Public Health · HEALTH | Dec 16, 2022 | Jan 9, 2023 | — |
Development fee collection Building Inspection · DFCU | Feb 13, 2023 | Feb 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 13, 2023 | Jan 8, 2025 | Administrative |
Addendum 1: Health (article 22b)
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | May 7, 2025 | May 16, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | May 16, 2025 | May 16, 2025 | Administrative |
Public Health HEALTH-MH | May 16, 2025 | May 19, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | May 16, 2025 | May 19, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | May 19, 2025 | Nov 25, 2025 | Administrative |
Addendum 2: Foundation, podium, superstructure
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 8, 2025 | Jan 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2025 | Jan 23, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jan 23, 2025 | Mar 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2025 | Jan 27, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Jan 23, 2025 | Mar 19, 2025 | Not Applicable |
Public health review Public Health · HEALTH | Jan 23, 2025 | Jan 24, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 23, 2025 | Feb 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 23, 2025 | Aug 1, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Apr 14, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 2, 2025 | Apr 2, 2025 | Approved-Stipulated |
Public health review Public Health · HEALTH | May 19, 2025 | May 19, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jun 10, 2025 | Jun 24, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 14, 2025 | Jul 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2025 | Jul 17, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jul 24, 2025 | Jul 24, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2025 | Jul 28, 2025 | Approved-Stipulated |
Public health review Public Health · HEALTH | Jul 25, 2025 | Jul 25, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jul 25, 2025 | Jul 25, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2025 | Nov 25, 2025 | Administrative |
Addendum 3: Architecture, landscape, mep
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jan 21, 2025 | Feb 4, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Feb 5, 2025 | Feb 5, 2025 | Administrative |
Plumbing plan check Building Inspection · PID-PC | Feb 5, 2025 | May 5, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Mar 4, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Mar 11, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Feb 5, 2025 | Feb 12, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Feb 5, 2025 | Feb 12, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 5, 2025 | Feb 19, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Feb 5, 2025 | Feb 12, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 5, 2025 | Feb 7, 2025 | Issued Comments |
Zoning review Planning · CP-ZOC | Feb 5, 2025 | Feb 14, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Feb 5, 2025 | Nov 7, 2025 | Administrative |
Street use and mapping Public Works · DPW-BSM | Feb 19, 2025 | Feb 19, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Apr 22, 2025 | Apr 25, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 22, 2025 | May 16, 2025 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Apr 24, 2025 | Apr 24, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 14, 2025 | May 14, 2025 | Issued Comments |
Public health review Public Health · HEALTH | May 22, 2025 | May 22, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 29, 2025 | May 29, 2025 | Approved |
Mechanical plan review quality control Building Inspection · MECH-QC | Jul 30, 2025 | Jul 30, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2025 | Aug 11, 2025 | Issued Comments |
Plumbing plan check Building Inspection · PID-PC | Aug 6, 2025 | Sep 4, 2025 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Aug 6, 2025 | Aug 15, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Aug 6, 2025 | Aug 8, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Aug 6, 2025 | Aug 6, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 6, 2025 | Aug 9, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Aug 6, 2025 | Aug 13, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 6, 2025 | Aug 11, 2025 | Issued Comments |
Public health review Public Health · HEALTH | Aug 6, 2025 | Aug 7, 2025 | Approved |
Zoning review Planning · CP-ZOC | Aug 6, 2025 | Oct 31, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2025 | Aug 15, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 15, 2025 | Oct 9, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2025 | Oct 3, 2025 | Approved |
Electrical plan review Building Inspection · MECH-E | Sep 17, 2025 | Sep 17, 2025 | Approved |
Public health review Public Health · HEALTH | Sep 19, 2025 | Sep 19, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2025 | Sep 22, 2025 | Approved |
Plumbing plan check Building Inspection · PID-PC | Oct 6, 2025 | Oct 6, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 9, 2025 | Oct 9, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 21, 2025 | Oct 27, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Oct 21, 2025 | Nov 4, 2025 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Nov 4, 2025 | Nov 6, 2025 | Approved-Stipulated |
Development fee collection Building Inspection · DFCU | Nov 7, 2025 | Nov 7, 2025 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 7, 2025 | Nov 25, 2025 | Administrative |
Addendum 4: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 17, 2026 | Aug 10, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2026 | Aug 11, 2026 | Administrative |
Fire Department housing review Fire Department · SFFD-HQ | Aug 11, 2026 | Aug 17, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 11, 2026 | In progress | — |
Fire Department housing review Fire Department · SFFD-HQ | Sep 9, 2026 | Sep 16, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Oct 14, 2026 | Oct 16, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | Nov 3, 2026 | Nov 3, 2026 | Issued Comments |
Fire Department housing review Fire Department · SFFD-HQ | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Addendum 8: Metal stairs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jun 30, 2026 | Jul 20, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 20, 2026 | Jul 20, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Jul 20, 2026 | Aug 19, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2026 | Aug 18, 2026 | Not Applicable |
Fire Department housing review Fire Department · SFFD-HQ | Jul 20, 2026 | Aug 5, 2026 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Jul 20, 2026 | Sep 28, 2026 | Administrative |
Building plan review quality control Building Inspection · BLDG-QC | Aug 24, 2026 | Aug 24, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Sep 17, 2026 | Sep 21, 2026 | Approved |
Fire Department housing review Fire Department · SFFD-HQ | Sep 17, 2026 | Sep 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 28, 2026 | Nov 3, 2026 | Administrative |
Addendum 9: Structural tie-downs
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Aug 6, 2026 | Aug 24, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 27, 2026 | Aug 27, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Aug 27, 2026 | Oct 9, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Aug 27, 2026 | Oct 9, 2026 | Not Applicable |
Permit Processing Center Building Inspection · PPC | Aug 27, 2026 | In progress | In Progress |
Building plan review Building Inspection · BLDG | Oct 14, 2026 | Oct 23, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction
- Status
- Issued
- Estimated cost
- $72,464,450
| Name | Role | License on permit |
|---|---|---|
| Karen E Murray Van Meter Williams Pollack Llp | Architect | C27052 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026