San Francisco permit 202207289526 · Sunset/Parkside

AdditionFull plan reviewComplete
Street view · Feb 2015
Google Street View of 1919 47th Av, Feb 2015
Scope of work
As written on the permit application.

2-story rear addition with primary bedroom suite, guest bedroom and family room. relocate & remodel 1st fl bath & laundry. remodel (e) 2nd fl bathroom. relocate 2nd fl kitchen. enlarge entry stairs. widen & recess garage door. widen entry gate. add deck & stair at rear of house.

Timeline
Key dates from the city record.
Filed
Jul 28, 2022
Issued
Oct 4, 2023 (14 months after filing)
Completed
May 1, 2026 (31 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
50 stops across 6 departments
Comments issued
11 times, by Building Inspection, Fire Department, Public Works
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Aug 4, 2022—

Zoning review

Planning · CP-ZOC

Sep 19, 2023Approved

Permit Processing Center

Building Inspection · PPC

Sep 25, 2023Administrative

Planning neighborhood notice

Planning · CP-NP

Jun 6, 2023—

Planning discretionary review

Planning · CP-DR

Jun 6, 2023—

Building plan review

Building Inspection · BLDG

Jul 18, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Aug 21, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jun 28, 2023—

Urban forestry

Public Works · DPW-BUF

Sep 20, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 23, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Aug 8, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 27, 2023Approved

Fire prevention review

Fire Department · SFFD

Aug 29, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 1, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 23, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Sep 1, 2023Administrative

Fire prevention review

Fire Department · SFFD

Sep 19, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 18, 2023Approved

Zoning review

Planning · CP-ZOC

Sep 6, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 7, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Sep 7, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Oct 4, 2023Administrative

Addendum 1: Final - foundation, structural, title 24/mechanical.

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Jan 25, 2024Approved

Permit Center

Permit Center · PERMIT-CTR

Jan 25, 2024Approved

Building pre-screening

Building Inspection · PRE-BLDG

Jan 18, 2024Approved

Mechanical pre-screening

Building Inspection · PRE-MECH

Jan 19, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Jan 31, 2024Administrative

Building plan review

Building Inspection · BLDG

Feb 27, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 26, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 15, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 21, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 1, 2024Approved

Permit Processing Center

Building Inspection · PPC

Aug 15, 2024Administrative

Building plan review

Building Inspection · BLDG

Jun 27, 2024Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 1, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jun 26, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 9, 2024Approved

Urban forestry

Public Works · DPW-BUF

Jul 24, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 10, 2024Approved

Building plan review

Building Inspection · BLDG

Jul 24, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Jul 19, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 17, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 23, 2024Approved

Structural plan approval

Building Inspection · PAD-STR

Aug 13, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Jul 26, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 29, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 29, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 19, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$653,759
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Judith Ann Mattingly

Mattingly Thaler Archit.

ArchitectC23854
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202207289526 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record