165 El Verano Wy
San Francisco permit 202208029763 · West of Twin Peaks
(n) 3rd story addition and roof deck. (n) 2nd story addition at north side yard.
- Filed
- Aug 2, 2022
- Issued
- Aug 30, 2024 (25 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 24 stops across 5 departments
- Comments issued
- 7 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Code enforcement Building Inspection · CES | Aug 2, 2022 | Aug 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2022 | Aug 12, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 12, 2022 | Jul 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 12, 2022 | Aug 2, 2024 | Administrative |
Planning neighborhood notice Planning · CP-NP | Apr 26, 2023 | Jun 9, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2023 | Aug 22, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2023 | Aug 3, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jul 6, 2023 | Jul 31, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2023 | Jan 23, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2023 | Jul 18, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 23, 2024 | Jan 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Feb 5, 2024 | Feb 12, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jun 28, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jun 21, 2024 | Jul 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 11, 2024 | Jul 24, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 11, 2024 | Jul 22, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 11, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 11, 2024 | Jul 18, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 11, 2024 | Jul 11, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 22, 2024 | Aug 1, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 22, 2024 | Jul 23, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 22, 2024 | Jul 22, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 22, 2024 | Jul 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 2, 2024 | Aug 30, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $513,074
| Name | Role | License on permit |
|---|---|---|
| Daniel Aaron Ewald Eta-Sf | Architect | C30585 |
| Zhuren Lawrence Liao Lawrence Liao Str. Eng | Engineer | S3273 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025