165 El Verano Wy

San Francisco permit 202208029763 · West of Twin Peaks

AdditionFull plan reviewIssued
Street view · Mar 2025
Google Street View of 165 El Verano Wy, Mar 2025
Scope of work
As written on the permit application.

(n) 3rd story addition and roof deck. (n) 2nd story addition at north side yard.

Timeline
Key dates from the city record.
Filed
Aug 2, 2022
Issued
Aug 30, 2024 (25 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
24 stops across 5 departments
Comments issued
7 times, by Building Inspection, Fire Department, Public Works
Put on hold
3 times
Review stopFinishedResult

Code enforcement

Building Inspection · CES

Aug 2, 2022—

Central Permit Bureau

Building Inspection · CPB

Aug 12, 2022—

Zoning review

Planning · CP-ZOC

Jul 6, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 2, 2024Administrative

Planning neighborhood notice

Planning · CP-NP

Jun 9, 2023—

Building plan review

Building Inspection · BLDG

Aug 22, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 3, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Jul 31, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jan 23, 2024Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jan 23, 2024Approved

Building plan review

Building Inspection · BLDG

Feb 12, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jun 28, 2024Issued Comments

Building plan review

Building Inspection · BLDG

Jul 15, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jul 24, 2024Approved

Fire prevention review

Fire Department · SFFD

Jul 22, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 18, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 11, 2024Approved

Building plan review

Building Inspection · BLDG

Aug 1, 2024Approved

Zoning review

Planning · CP-ZOC

Jul 23, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Jul 22, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jul 31, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Aug 30, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$513,074
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Daniel Aaron Ewald

Eta-Sf

ArchitectC30585
Zhuren Lawrence Liao

Lawrence Liao Str. Eng

EngineerS3273
Sources