6 San Pablo Av
San Francisco permit 202208050034 · West of Twin Peaks
Proposed remodel & horizontal addition with structural,plumbing & electrical work. replacement & new windows on front,sides and rear.
- Filed
- Aug 5, 2022
- Issued
- Jun 28, 2023 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 26 stops across 4 departments
- Comments issued
- 3 times, by Building Inspection, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 5, 2022 | Aug 8, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 8, 2022 | Mar 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 8, 2022 | Jun 15, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 16, 2023 | May 18, 2023 | — |
Structural plan approval Building Inspection · PAD-STR | Mar 16, 2023 | May 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 16, 2023 | Mar 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 16, 2023 | Apr 10, 2023 | — |
Building plan review Building Inspection · BLDG | May 18, 2023 | May 18, 2023 | — |
Zoning review Planning · CP-ZOC | May 31, 2023 | Jun 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 31, 2023 | Jun 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 31, 2023 | Jun 15, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 15, 2023 | Jun 28, 2023 | — |
Addendum 1: Arch,mech,struc,t-24,final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jul 6, 2023 | Jul 6, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 6, 2023 | Aug 8, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 6, 2023 | Aug 14, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 6, 2023 | Aug 14, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 6, 2023 | Jul 13, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jul 6, 2023 | Oct 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 7, 2023 | Sep 19, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 7, 2023 | Sep 14, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 7, 2023 | Oct 17, 2023 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Sep 7, 2023 | Oct 10, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 7, 2023 | Sep 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 19, 2023 | Oct 11, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2023 | Sep 25, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 17, 2023 | Oct 20, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $815,000
| Name | Role | License on permit |
|---|---|---|
| Howard E Blecher | Architect | C36464 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2022