115 Gennessee St
San Francisco permit 202208080110 · West of Twin Peaks
1st and 2nd floor horizontal addition, interior remodel. new backyard hardscape.
- Filed
- Aug 8, 2022
- Issued
- Aug 11, 2023 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 21 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection, Public Works, Public Utilities
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 8, 2022 | Jun 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2022 | Jun 21, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 25, 2022 | Feb 22, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Dec 21, 2022 | Feb 22, 2023 | — |
Building plan review Building Inspection · BLDG | May 9, 2023 | Jun 16, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 9, 2023 | May 23, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 9, 2023 | Jun 21, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 21, 2023 | Aug 11, 2023 | Administrative |
Addendum 1: Grading,foundation,t-24,mep,final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 21, 2023 | Aug 21, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Aug 21, 2023 | Sep 15, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2023 | Sep 22, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 21, 2023 | Aug 31, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 21, 2023 | Aug 24, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Aug 21, 2023 | Jan 8, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2023 | Sep 12, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 14, 2023 | Sep 14, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Dec 12, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 12, 2023 | Dec 12, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 15, 2023 | Dec 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2023 | Jan 8, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 8, 2024 | Jan 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $364,000
| Name | Role | License on permit |
|---|---|---|
| Antje Paiz | Architect | C31989 |
| Peter David Bonneau Structural Design | Engineer | 81545 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2021