258 12th Av
San Francisco permit 202208080115 · Inner Richmond
Single family residential interior remodel. two story rear yard addition, and revised back exterior deck.
- Filed
- Aug 8, 2022
- Issued
- Nov 28, 2023 (16 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 29 stops across 4 departments
- Comments issued
- 4 times, by Building Inspection
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 8, 2022 | Aug 16, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 16, 2022 | Apr 5, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 16, 2022 | Nov 14, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Feb 2, 2023 | Apr 5, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 7, 2023 | May 22, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 7, 2023 | Sep 19, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Apr 7, 2023 | Apr 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 7, 2023 | May 12, 2023 | — |
Zoning review Planning · CP-ZOC | May 4, 2023 | Sep 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 4, 2023 | Oct 2, 2023 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Sep 19, 2023 | Oct 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 19, 2023 | Oct 20, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 19, 2023 | Oct 19, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 19, 2023 | Nov 8, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 7, 2023 | Nov 8, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 7, 2023 | Nov 13, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 14, 2023 | Nov 28, 2023 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Dec 4, 2023 | Dec 4, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Dec 4, 2023 | Feb 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 4, 2023 | Jan 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Dec 4, 2023 | Dec 5, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 4, 2023 | Dec 6, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 4, 2023 | Mar 18, 2024 | — |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Mar 4, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Feb 26, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Feb 22, 2024 | Mar 4, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 22, 2024 | Feb 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 6, 2024 | Mar 6, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 18, 2024 | Mar 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $440,834
| Name | Role | License on permit |
|---|---|---|
| Mia K Zinni | Architect | C39469 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025