202 Fair Oaks St #0
San Francisco permit 202208120467 · Mission
Interior work at 202: add full bathroom at 3rd fl. add new skylight, replace pickets at rear stairs
- Filed
- Aug 12, 2022
- Issued
- Dec 3, 2024 (28 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 3 departments
- Comments issued
- 4 times, by Building Inspection, Public Utilities
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 12, 2022 | Aug 15, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 15, 2022 | Dec 27, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 15, 2022 | Oct 11, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 29, 2022 | Feb 9, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 29, 2022 | Sep 5, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Dec 29, 2022 | Jan 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 18, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 18, 2024 | Jul 18, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 13, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 4, 2024 | Sep 6, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 5, 2024 | Sep 5, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 5, 2024 | Sep 5, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 16, 2024 | Sep 16, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2024 | Sep 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Sep 16, 2024 | Sep 17, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 19, 2024 | Sep 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 11, 2024 | Dec 3, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Expired
- Estimated cost
- $35,000
| Name | Role | License on permit |
|---|---|---|
| Jonathan N Pearlman Elevation Architects | Architect | C26034 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2019