4 Embarcadero Center
San Francisco permit 202208120488 · Financial District/South Beach
1st fl tenant improvement for fedex office store. new finishes, graphics, lighting, new and relocated fixtures, equipment, relocated plumbing fixture, new mop sink, new restroom accessories, distribution of phone and pwr/data to equipment. mod mech, elec, plumbing work and mod to sprinkler/fire sys
- Filed
- Aug 12, 2022
- Issued
- Mar 28, 2023 (7 months after filing)
- Completed
- Aug 14, 2023 (5 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 16 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 12, 2022 | Sep 16, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 16, 2022 | Oct 26, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 16, 2022 | Feb 8, 2023 | — |
Building plan review Building Inspection · BLDG | Nov 1, 2022 | Jan 4, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 1, 2022 | Jan 30, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Nov 1, 2022 | Nov 2, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 1, 2022 | Nov 7, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Nov 28, 2022 | Nov 28, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Nov 28, 2022 | Jan 30, 2023 | — |
Fire prevention review Fire Department · SFFD | Nov 28, 2022 | Jan 31, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2023 | Feb 1, 2023 | — |
Zoning review Planning · CP-ZOC | Feb 1, 2023 | Feb 8, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 1, 2023 | Feb 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 1, 2023 | Feb 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 1, 2023 | Feb 1, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 8, 2023 | Mar 28, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $434,835
| Name | Role | License on permit |
|---|---|---|
| Richard H Sweers Richard Sweers | Architect | C17689 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2017