415 Grafton Av
San Francisco permit 202208150509 · Oceanview/Merced/Ingleside
2nd story addition rear of home. upstairs addition to include 2 bedrooms, 2 bathrooms, 1 laundry room. downstairs remodel to include new full bathroom, kitchen expansion, new family room. - deck remodel at backyard.
- Filed
- Aug 15, 2022
- Issued
- Nov 15, 2023 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 46 stops across 6 departments
- Comments issued
- 10 times, by Building Inspection, Permit Center, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 19, 2022 | Aug 24, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 24, 2022 | May 11, 2023 | — |
Permit Processing Center Building Inspection · PPC | Aug 24, 2022 | Nov 2, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Dec 12, 2022 | Jan 30, 2023 | — |
Planning discretionary review Planning · CP-DR | Jan 26, 2023 | Mar 31, 2023 | — |
Building plan review Building Inspection · BLDG | May 12, 2023 | Aug 7, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 12, 2023 | Sep 11, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | May 12, 2023 | May 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 12, 2023 | Jun 9, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 19, 2023 | Jul 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 19, 2023 | Aug 14, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 19, 2023 | Jul 26, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2023 | Aug 10, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Aug 4, 2023 | Aug 9, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 10, 2023 | Aug 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Sep 22, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2023 | Oct 18, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2023 | Sep 14, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 8, 2023 | Sep 8, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Sep 25, 2023 | Sep 25, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2023 | Nov 15, 2023 | Administrative |
Addendum 1: Final - t24, structural, foundation
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Feb 28, 2024 | Mar 11, 2024 | Issued Comments |
Central Permit Bureau Building Inspection · CPB | Feb 29, 2024 | Mar 19, 2024 | Administrative |
Building pre-screening Building Inspection · PRE-BLDG | Mar 1, 2024 | Mar 1, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Mar 1, 2024 | Mar 1, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Mar 19, 2024 | Mar 19, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 19, 2024 | May 9, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 19, 2024 | Apr 24, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 19, 2024 | Mar 27, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 19, 2024 | Sep 12, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Mar 20, 2024 | Mar 28, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 12, 2024 | Jul 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2024 | Jul 16, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 12, 2024 | Jul 15, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 23, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 24, 2024 | Jul 30, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2024 | Jul 29, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 24, 2024 | Jul 24, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 24, 2024 | Jul 24, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2024 | Jul 30, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 30, 2024 | Aug 5, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jul 30, 2024 | Aug 6, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 30, 2024 | Jul 31, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 30, 2024 | Aug 7, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 15, 2024 | Aug 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 12, 2024 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Reinstated
- Estimated cost
- $500,000
| Name | Role | License on permit |
|---|---|---|
| Tyler Gleeson Kobick Design Draw Build | Architect | C36432 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011