221 04th St
San Francisco permit 202208150511 · South of Market
Ti including 5 new offices and 1 meeting room no structural or plumbing scope. change of use groud floor
- Filed
- Aug 15, 2022
- Issued
- Oct 18, 2022 (2 months after filing)
- Completed
- Mar 31, 2023 (5 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 11 stops across 5 departments
- Comments issued
- Not recorded for this permit
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 15, 2022 | Aug 15, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 15, 2022 | Aug 15, 2022 | — |
Disability access review Mayor's Office on Disability · MOD | Aug 22, 2022 | Oct 3, 2022 | — |
Intake Building Inspection · INTAKE | Oct 5, 2022 | Oct 5, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 5, 2022 | Oct 5, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 5, 2022 | Oct 5, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 5, 2022 | Oct 5, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Oct 5, 2022 | Oct 5, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 5, 2022 | Oct 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 5, 2022 | Oct 5, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 18, 2022 | Oct 18, 2022 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $73,604
| Name | Role | License on permit |
|---|---|---|
| Heather Demaree Sanders-Jacob Shelterwerk | Architect | C-29638 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025