67 A Mirabel Av
San Francisco permit 202208160608 · Bernal Heights
Interior remodel @ (e) 2 dwelling units located @ 1st & 2nd flr that includes: 2nd flr: add (n) bath & (n) bedroom to create a 2bed/2 bath unit. remodel (e) kitchen. 1st flr: reconfigure interior layout to create a 2bed/2bath unit.no changes to (e) 2 levls of basement space.(e) bldg is not sprinkler
- Filed
- Aug 16, 2022
- Issued
- Jun 21, 2023 (10 months after filing)
- Completed
- Nov 7, 2025 (29 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 16, 2022 | Aug 16, 2022 | — |
Permit Processing Center Building Inspection · PPC | Aug 16, 2022 | Jun 14, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 17, 2022 | Jan 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 17, 2022 | Apr 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Aug 17, 2022 | Sep 2, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Aug 17, 2022 | Aug 17, 2022 | — |
Building plan review Building Inspection · BLDG | Jan 17, 2023 | May 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 17, 2023 | Jan 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2023 | Apr 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 21, 2023 | Mar 24, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 28, 2023 | Apr 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 19, 2023 | May 1, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 2, 2023 | May 2, 2023 | — |
Fire prevention review Fire Department · SFFD | May 2, 2023 | May 23, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 2, 2023 | May 4, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 2, 2023 | Jun 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 14, 2023 | Jun 21, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $460,000
| Name | Role | License on permit |
|---|---|---|
| Yogesh Chitlangia Yogesh Chitlangia Architect | Architect | C31132 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023