557 Anderson St
San Francisco permit 202208241149 · Bernal Heights
Conditioning of ground floor garage,new bath office,media & storage area.415 sq ft of new habitable space.single parking spot in garage to remain.new interior stair from level 1 to 2.
- Filed
- Aug 24, 2022
- Issued
- Sep 11, 2024 (25 months after filing)
- Completed
- Oct 6, 2025 (13 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 14 stops across 4 departments
- Comments issued
- None
- Put on hold
- 3 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 24, 2022 | Sep 13, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 13, 2022 | Oct 28, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 13, 2022 | Feb 3, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 31, 2022 | Jan 17, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 31, 2022 | Dec 5, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 31, 2022 | Nov 2, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 31, 2022 | Nov 2, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 30, 2022 | Dec 7, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Nov 30, 2022 | Dec 1, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Nov 30, 2022 | Feb 1, 2023 | — |
Zoning review Planning · CP-ZOC | Jan 17, 2023 | Jan 18, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 17, 2023 | Jan 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 17, 2023 | Jan 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Feb 3, 2023 | Sep 11, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $180,000
| Name | Role | License on permit |
|---|---|---|
| Aurelio Torres Alegria Alegria Structural Engineer | Engineer | S2746 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025