284 Page St
San Francisco permit 202208291433 · Hayes Valley
Interior remodel to (e) bathrooms & kitchen. convert unconditioned ground floor into conditioned space: new cabinets, lighting, fixtures, finishes. 2 new patio doors on rear elevation, 1 new skylight. no change to lily st apts.
- Filed
- Aug 29, 2022
- Issued
- Jun 15, 2023 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 15 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Aug 29, 2022 | Aug 29, 2022 | — |
Zoning review Planning · CP-ZOC | Aug 29, 2022 | Aug 29, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Aug 29, 2022 | Aug 29, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2022 | Sep 23, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 23, 2022 | Sep 23, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 26, 2022 | Nov 14, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 3, 2022 | Nov 3, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 15, 2022 | Mar 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 5, 2023 | Jan 6, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2023 | Jan 18, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 17, 2023 | Mar 17, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 20, 2023 | Mar 29, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2023 | Apr 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Apr 3, 2023 | Apr 3, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2023 | Jun 15, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $785,000
| Name | Role | License on permit |
|---|---|---|
| Javier Medina Mark Davis Design | Architect | C34033 |
| Kathryn Briggs Base Design | Engineer | 5732 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2022