23 07th Av
San Francisco permit 202208291513 · Inner Richmond
Interior remodel of an (e) single family residence. includes a foundation replacement, altered fenestrations at rear of house, several exterior volumetric additions not visible from front of property, and new skylights at the roof.
- Filed
- Aug 29, 2022
- Issued
- Sep 8, 2023 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 33 stops across 5 departments
- Comments issued
- 4 times, by Building Inspection, Fire Department, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 29, 2022 | Sep 7, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 7, 2022 | Apr 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2022 | Aug 31, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 28, 2023 | Apr 14, 2023 | — |
Building plan review Building Inspection · BLDG | Apr 17, 2023 | Jul 6, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 17, 2023 | Aug 25, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Apr 17, 2023 | Apr 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 17, 2023 | May 16, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2023 | Jul 11, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 27, 2023 | Jun 27, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 27, 2023 | Jun 28, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 27, 2023 | Jul 11, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 7, 2023 | Jul 7, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 7, 2023 | Jul 27, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Jul 7, 2023 | Jul 11, 2023 | — |
Zoning review Planning · CP-ZOC | Aug 4, 2023 | Aug 5, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 7, 2023 | Aug 8, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 7, 2023 | Aug 28, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 7, 2023 | Aug 9, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 31, 2023 | Sep 8, 2023 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 8, 2024 | Jan 8, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 8, 2024 | Feb 27, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 8, 2024 | Jan 31, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 8, 2024 | Mar 6, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jan 8, 2024 | Jan 24, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 8, 2024 | Jan 9, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 8, 2024 | In progress | — |
Structural plan approval Building Inspection · PAD-STR | Feb 15, 2024 | Apr 9, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | — | In progress | — |
Mechanical and energy plan review Building Inspection · MECH | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Street use and mapping Public Works · DPW-BSM | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $1,249,405
| Name | Role | License on permit |
|---|---|---|
| Malcolm Christopher Davis Malcolm Davis Architecture | Architect | C23744 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011