1632 20th St
San Francisco permit 202208311657 · Potrero Hill
Horizontal and vertical addition. interior renovations on all floors. new decks and facade alterations.
- Filed
- Aug 31, 2022
- Issued
- Sep 19, 2023 (13 months after filing)
- Completed
- Apr 14, 2026 (31 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 4 departments
- Comments issued
- Once, by Building Inspection
- Put on hold
- 5 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Aug 31, 2022 | Sep 1, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 1, 2022 | Jan 20, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 1, 2022 | Sep 7, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | Dec 6, 2022 | Jan 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 24, 2023 | Aug 3, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jan 24, 2023 | Apr 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 24, 2023 | May 3, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 24, 2023 | Feb 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 13, 2023 | Jun 29, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 29, 2023 | Jun 29, 2023 | — |
Building plan review Building Inspection · BLDG | Aug 23, 2023 | Aug 23, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 24, 2023 | Aug 24, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 24, 2023 | Sep 5, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 24, 2023 | Aug 28, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 24, 2023 | Aug 25, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 6, 2023 | Sep 7, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 7, 2023 | Sep 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $1,800,000
| Name | Role | License on permit |
|---|---|---|
| Joyce Feng Strandberg Engineering | Engineer | S4856 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2021