San Francisco permit 202209021794 · Tenderloin
Selective demo & new construction required to connect an (e) electrical fire pump at garage level. selective demo removal of (e) diesel fire pump + some walls, doors, mechanical and electrical equipment. new electrical equipment: a new switchgear to be located in switchboard room at garage level.
- Filed
- Sep 2, 2022
- Issued
- Mar 9, 2023 (6 months after filing)
- Completed
- Oct 27, 2023 (8 months after issuance)
- Review stops
- 13 stops across 2 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 4 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 2, 2022 | Sep 2, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 2, 2022 | Sep 7, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 7, 2022 | Mar 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 7, 2022 | Dec 5, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Sep 7, 2022 | Dec 23, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 7, 2022 | Mar 6, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 7, 2022 | Mar 7, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 5, 2022 | Feb 7, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Dec 23, 2022 | Dec 23, 2022 | — |
Electrical plan review Building Inspection · MECH-E | Feb 1, 2023 | Feb 8, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2023 | Feb 7, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 22, 2023 | Mar 7, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Mar 7, 2023 | Mar 9, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| William Stuart Lyle Sgpa Arch & Planning | Architect | C24741 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026