San Francisco permit 202209021852 · Pacific Heights

Commercial or tenant improvementFull plan reviewIssued
Street view · Jan 2025
Google Street View of 1950 Jackson St, Jan 2025
Scope of work
As written on the permit application.

Phase 3:will return building to a residence & will include the following scope of work:limited demolition,finishes,bathroom & kitchen work. sprinklers,seismic,major mep & security work will occur in an earlier phase,under a separage permit.this work will return the bldg to original r-3 occupancy.

Timeline
Key dates from the city record.
Filed
Sep 2, 2022
Issued
Jan 3, 2023 (4 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
27 stops across 5 departments
Comments issued
Twice, by Building Inspection
Put on hold
4 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 17, 2022—

Zoning review

Planning · CP-ZOC

Nov 29, 2022—

Building plan review

Building Inspection · BLDG

Nov 1, 2022—

Fire prevention review

Fire Department · SFFD

Nov 3, 2022—

Street use and mapping

Public Works · DPW-BSM

Dec 15, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Nov 4, 2022—

Permit Processing Center

Building Inspection · PPC

Dec 20, 2022—

Zoning review

Planning · CP-ZOC

Dec 19, 2022—

Central Permit Bureau

Building Inspection · CPB

Jan 3, 2023—

Addendum 1: Final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Jan 12, 2023—

Building plan review

Building Inspection · BLDG

Jun 21, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 12, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 22, 2023—

Fire prevention review

Fire Department · SFFD

Jan 18, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 23, 2023—

Permit Processing Center

Building Inspection · PPC

Aug 11, 2023—

Electrical plan review

Building Inspection · MECH-E

Mar 17, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Jun 28, 2023—

Mechanical and energy plan review

Building Inspection · MECH

Jul 12, 2023—

Building plan review

Building Inspection · BLDG

Aug 2, 2023Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jul 20, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jul 20, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 21, 2023—

Electrical plan review

Building Inspection · MECH-E

Aug 2, 2023Approved

Building plan review

Building Inspection · BLDG

Aug 3, 2023Approved

Fire prevention review

Fire Department · SFFD

Aug 7, 2023Administrative

Central Permit Bureau

Building Inspection · CPB

Sep 19, 2023Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$1,000,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Nancy Gail Goldenberg

Treanorhl

ArchitectC25019
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202209021852 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record