1950 Jackson St
San Francisco permit 202209021852 · Pacific Heights
Phase 3:will return building to a residence & will include the following scope of work:limited demolition,finishes,bathroom & kitchen work. sprinklers,seismic,major mep & security work will occur in an earlier phase,under a separage permit.this work will return the bldg to original r-3 occupancy.
- Filed
- Sep 2, 2022
- Issued
- Jan 3, 2023 (4 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 27 stops across 5 departments
- Comments issued
- Twice, by Building Inspection
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 2, 2022 | Oct 17, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 28, 2022 | Nov 29, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 28, 2022 | Nov 1, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 28, 2022 | Nov 3, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 28, 2022 | Dec 15, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 28, 2022 | Nov 4, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 28, 2022 | Dec 20, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 19, 2022 | Dec 19, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Dec 20, 2022 | Jan 3, 2023 | — |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 12, 2023 | Jan 12, 2023 | — |
Building plan review Building Inspection · BLDG | Jan 13, 2023 | Jun 21, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jan 13, 2023 | Jul 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jan 13, 2023 | Jun 22, 2023 | — |
Fire prevention review Fire Department · SFFD | Jan 13, 2023 | Jan 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jan 13, 2023 | Jan 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | Jan 13, 2023 | Aug 11, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 13, 2023 | Mar 17, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 28, 2023 | Jun 28, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jul 12, 2023 | Jul 12, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 20, 2023 | Aug 2, 2023 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 20, 2023 | Jul 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 20, 2023 | Jul 20, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 21, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Aug 2, 2023 | Aug 2, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 3, 2023 | Aug 3, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 7, 2023 | Aug 7, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 11, 2023 | Sep 19, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,000,000
| Name | Role | License on permit |
|---|---|---|
| Nancy Gail Goldenberg Treanorhl | Architect | C25019 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2025