333 Dolores St
San Francisco permit 202209071941 · Mission
Erect a 1 story preschool bldg,no dwelling,no basement.type -v
- Filed
- Sep 7, 2022
- Issued
- May 4, 2023 (8 months after filing)
- Completed
- Nov 27, 2024 (19 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 62 stops across 6 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department
- Put on hold
- 13 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 7, 2022 | Sep 15, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 15, 2022 | Mar 17, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 15, 2022 | Apr 24, 2023 | — |
Building plan review Building Inspection · BLDG | Dec 9, 2022 | Apr 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 9, 2022 | Mar 17, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Dec 9, 2022 | Dec 14, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 9, 2022 | Jan 6, 2023 | — |
Public health review Public Health · HEALTH | Dec 15, 2022 | Mar 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 17, 2023 | Mar 27, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 24, 2023 | Apr 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 27, 2023 | Apr 14, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2023 | Apr 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Apr 14, 2023 | Apr 17, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Apr 14, 2023 | Apr 17, 2023 | — |
Development fee collection Building Inspection · DFCU | Apr 17, 2023 | Apr 17, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Apr 18, 2023 | May 4, 2023 | — |
Urban forestry Public Works · DPW-BUF | Apr 19, 2023 | Apr 21, 2023 | — |
Addendum 1: Health
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 23, 2023 | May 23, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 23, 2023 | Jun 13, 2023 | — |
Public health review Public Health · HEALTH | May 24, 2023 | Jun 13, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 13, 2023 | Aug 3, 2023 | Administrative |
Addendum 2: Foundation,structural,grading
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 11, 2023 | May 15, 2023 | — |
Building plan review Building Inspection · BLDG | May 15, 2023 | Jul 25, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | Jun 7, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2023 | Jul 31, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Jul 25, 2023 | Jul 31, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jul 31, 2023 | Aug 3, 2023 | Administrative |
Addendum 3: Architectural,mep,site
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | May 11, 2023 | May 15, 2023 | — |
Building plan review Building Inspection · BLDG | May 15, 2023 | Aug 21, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2023 | Aug 23, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 15, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | Jun 7, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2023 | May 19, 2023 | — |
Zoning review Planning · CP-ZOC | May 15, 2023 | May 16, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 15, 2023 | Nov 2, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 22, 2023 | Jul 12, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 22, 2023 | Jul 24, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Aug 16, 2023 | Aug 16, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Aug 23, 2023 | Aug 23, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 12, 2023 | Sep 21, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 10, 2023 | Oct 10, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 24, 2023 | Oct 24, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Oct 25, 2023 | Oct 30, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 25, 2023 | Oct 27, 2023 | Issued Comments |
Electrical plan review Building Inspection · MECH-E | Oct 25, 2023 | Oct 26, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2023 | Nov 1, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2023 | Oct 30, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 25, 2023 | Oct 31, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 30, 2023 | Oct 30, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 2, 2023 | Nov 15, 2023 | Administrative |
Addendum 4: Fire alarm
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Nov 27, 2023 | Nov 27, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Nov 27, 2023 | Nov 29, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Nov 27, 2023 | Apr 26, 2024 | — |
Fire prevention review Fire Department · SFFD | Mar 1, 2024 | Mar 1, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 25, 2024 | Apr 25, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 26, 2024 | May 1, 2024 | Administrative |
Addendum 5: Fire sprinklers
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 13, 2023 | Oct 13, 2023 | Administrative |
Fire prevention review Fire Department · SFFD | Oct 13, 2023 | Oct 17, 2023 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Oct 13, 2023 | Apr 17, 2024 | — |
Fire prevention review Fire Department · SFFD | Nov 6, 2023 | Mar 4, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 17, 2024 | Apr 17, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 17, 2024 | Apr 18, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $7,500,000
| Name | Role | License on permit |
|---|---|---|
| Mark Thomas Jensen Jensen Architects | Architect | C21410 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2016