San Francisco permit 202209071941 · Mission

New buildingFull plan reviewComplete
Street view · Mar 2016
Google Street View of 333 Dolores St, Mar 2016
Scope of work
As written on the permit application.

Erect a 1 story preschool bldg,no dwelling,no basement.type -v

Timeline
Key dates from the city record.
Filed
Sep 7, 2022
Issued
May 4, 2023 (8 months after filing)
Completed
Nov 27, 2024 (19 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
62 stops across 6 departments
Comments issued
9 times, by Building Inspection, Fire Department
Put on hold
13 times

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Sep 15, 2022—

Zoning review

Planning · CP-ZOC

Mar 17, 2023—

Permit Processing Center

Building Inspection · PPC

Apr 24, 2023—

Building plan review

Building Inspection · BLDG

Apr 14, 2023—

Fire prevention review

Fire Department · SFFD

Mar 17, 2023—

Street use and mapping

Public Works · DPW-BSM

Dec 14, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Jan 6, 2023—

Public health review

Public Health · HEALTH

Mar 20, 2023—

Fire prevention review

Fire Department · SFFD

Mar 27, 2023—

Building plan review

Building Inspection · BLDG

Apr 14, 2023—

Fire prevention review

Fire Department · SFFD

Apr 14, 2023—

Fire prevention review

Fire Department · SFFD

Apr 14, 2023—

Street use and mapping

Public Works · DPW-BSM

Apr 17, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Apr 17, 2023—

Development fee collection

Building Inspection · DFCU

Apr 17, 2023—

Central Permit Bureau

Building Inspection · CPB

May 4, 2023—

Urban forestry

Public Works · DPW-BUF

Apr 21, 2023—

Addendum 1: Health

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 23, 2023—

Permit Processing Center

Building Inspection · PPC

Jun 13, 2023—

Public health review

Public Health · HEALTH

Jun 13, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 3, 2023Administrative

Addendum 2: Foundation,structural,grading

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 15, 2023—

Building plan review

Building Inspection · BLDG

Jul 25, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2023—

Permit Processing Center

Building Inspection · PPC

Jul 31, 2023Administrative

Street use and mapping

Public Works · DPW-BSM

Jul 31, 2023—

Central Permit Bureau

Building Inspection · CPB

Aug 3, 2023Administrative

Addendum 3: Architectural,mep,site

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

May 15, 2023—

Building plan review

Building Inspection · BLDG

Aug 21, 2023Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Issued Comments

Fire prevention review

Fire Department · SFFD

Jun 22, 2023—

Street use and mapping

Public Works · DPW-BSM

Jun 7, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

May 19, 2023—

Zoning review

Planning · CP-ZOC

May 16, 2023—

Permit Processing Center

Building Inspection · PPC

Nov 2, 2023—

Electrical plan review

Building Inspection · MECH-E

Jul 12, 2023—

Fire prevention review

Fire Department · SFFD

Jul 24, 2023—

Electrical plan review

Building Inspection · MECH-E

Aug 16, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Aug 23, 2023Approved

Building plan review

Building Inspection · BLDG

Sep 21, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 10, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Oct 24, 2023Approved

Fire prevention review

Fire Department · SFFD

Oct 30, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 27, 2023Issued Comments

Electrical plan review

Building Inspection · MECH-E

Oct 26, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Nov 1, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Oct 30, 2023Approved

Zoning review

Planning · CP-ZOC

Oct 31, 2023Approved

Mechanical and energy plan review

Building Inspection · MECH

Oct 30, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Nov 15, 2023Administrative

Addendum 4: Fire alarm

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 27, 2023Administrative

Fire prevention review

Fire Department · SFFD

Nov 29, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Apr 26, 2024—

Fire prevention review

Fire Department · SFFD

Mar 1, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 25, 2024Approved

Central Permit Bureau

Building Inspection · CPB

May 1, 2024Administrative

Addendum 5: Fire sprinklers

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 13, 2023Administrative

Fire prevention review

Fire Department · SFFD

Oct 17, 2023Issued Comments

Permit Processing Center

Building Inspection · PPC

Apr 17, 2024—

Fire prevention review

Fire Department · SFFD

Mar 4, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Apr 17, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Apr 18, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
New construction wood frame
Status
Complete
Estimated cost
$7,500,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Mark Thomas Jensen

Jensen Architects

ArchitectC21410
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202209071941 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record