680 Sanchez St
San Francisco permit 202209082053 · Castro/Upper Market
Interior remodel, foundation replacement, lowering of 1st floor level, new inteiror stairs. exterior work: revised front facace, removal at entry stair, new fenestration & skylights.
- Filed
- Sep 8, 2022
- Issued
- Aug 21, 2023 (11 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 13 stops across 4 departments
- Comments issued
- None
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 8, 2022 | Sep 8, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 22, 2022 | Sep 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 22, 2022 | Sep 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 27, 2022 | Sep 27, 2022 | — |
Permit Center Permit Center · PERMIT-CTR | Sep 28, 2022 | Sep 28, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Oct 3, 2022 | Oct 17, 2022 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2022 | May 19, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 13, 2022 | Dec 27, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | May 19, 2023 | May 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 22, 2023 | May 23, 2023 | — |
Zoning review Planning · CP-ZOC | May 23, 2023 | May 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | May 25, 2023 | May 25, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 25, 2023 | Aug 21, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $588,263
| Name | Role | License on permit |
|---|---|---|
| Karen F Curtiss Red Dot Studio Architecture | Architect | C31453 |
| Shaun Edward Moynahan Semco Engineering Inc. | Engineer | S-4605 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025