3250 19th Av
San Francisco permit 202209082129 · West of Twin Peaks
Priority process - interior & exterior remodel: structural seismic retrofit, accommodating per-school & elementary classrooms, & provide accessible toilet rooms fpr staff & students. sitework: remove & construct in (n) play areas(landscape/hardscape/play trucrures/basketball courts/fences/gates.
- Filed
- Sep 8, 2022
- Issued
- Jun 28, 2023 (10 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 19 stops across 5 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 8 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 8, 2022 | Sep 9, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 9, 2022 | Mar 3, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 9, 2022 | Jun 27, 2023 | — |
Building plan review Building Inspection · BLDG | Feb 16, 2023 | Jun 13, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2023 | May 5, 2023 | — |
Electrical plan review Building Inspection · MECH-E | Feb 16, 2023 | May 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Feb 16, 2023 | Jun 12, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Feb 16, 2023 | Feb 22, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Feb 16, 2023 | Mar 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 5, 2023 | Jun 5, 2023 | — |
Electrical plan review Building Inspection · MECH-E | May 15, 2023 | Jun 7, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 1, 2023 | Jun 20, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2023 | Jun 8, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Jun 8, 2023 | Jun 8, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 20, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 20, 2023 | Jun 21, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 20, 2023 | Jun 21, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 22, 2023 | Jun 27, 2023 | — |
Central Permit Bureau Building Inspection · CPB | Jun 27, 2023 | Jun 28, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,200,000
| Name | Role | License on permit |
|---|---|---|
| Laura N Rambin Studio Bondy Architecture | Architect | C27742 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026