2443 24th St
San Francisco permit 202209092193 · Mission
Response to planning enforcement #2019-017865enf, #2020012068enf, #2022003345enf: conversion of (e) basement(current use for storage) to habitable space(1 bedroom and storage) connected to recently issued permti#201810193667.
- Filed
- Sep 9, 2022
- Issued
- Dec 23, 2025 (39 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 36 stops across 5 departments
- Comments issued
- 12 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 9, 2022 | Jul 28, 2023 | Administrative |
Building inspector Building Inspection · BID-INSP | Jul 19, 2023 | Jul 19, 2023 | — |
Code enforcement Building Inspection · CES | Jul 20, 2023 | Jul 20, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 28, 2023 | Aug 1, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jul 28, 2023 | Aug 1, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 14, 2024 | Apr 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 14, 2024 | Apr 29, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 14, 2024 | Apr 3, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 14, 2024 | Mar 20, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Mar 14, 2024 | Apr 2, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Aug 1, 2024 | Aug 14, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Aug 2, 2024 | Aug 2, 2024 | Approved |
Building plan review Building Inspection · BLDG | Aug 15, 2024 | Aug 15, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 15, 2024 | Aug 15, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Aug 21, 2024 | Aug 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2024 | Sep 9, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 10, 2024 | Sep 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 12, 2024 | Sep 18, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Nov 15, 2024 | Nov 15, 2024 | Approved |
Zoning review Planning · CP-ZOC | May 1, 2025 | May 6, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 1, 2025 | May 6, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 1, 2025 | May 2, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 1, 2025 | May 5, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 1, 2025 | May 5, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 1, 2025 | May 1, 2025 | Approved |
Zoning review Planning · CP-ZOC | May 21, 2025 | May 21, 2025 | Approved |
Building plan review Building Inspection · BLDG | May 21, 2025 | Jun 10, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 21, 2025 | May 22, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 21, 2025 | May 27, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | May 21, 2025 | Jun 10, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | May 21, 2025 | May 28, 2025 | Approved |
Building inspector Building Inspection · BID-INSP | May 22, 2025 | Aug 1, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2025 | May 27, 2025 | Approved |
Fire prevention review Fire Department · SFFD | May 27, 2025 | May 27, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Aug 1, 2025 | Dec 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $50,000
| Name | Role | License on permit |
|---|---|---|
| Thomas Steven Podesta Thomas Podesta Engineer | Engineer | C-37028 |
| John C Lee | Architect | C6896 |
| Rodrigo Santos Rs Engineering | Engineer | S2984 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024