680 Filbert St
San Francisco permit 202209132308 · North Beach
Including but not limited to: upper level play yard chain link fabric, including vehicular & pedestrian gate replacements, & lower level parking garage facade replacement.
- Filed
- Sep 13, 2022
- Issued
- May 26, 2023 (8 months after filing)
- Completed
- Nov 4, 2024 (17 months after issuance)
- Review stops
- 12 stops across 4 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- 3 times
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 13, 2022 | Sep 21, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 21, 2022 | Oct 20, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 21, 2022 | May 23, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 24, 2022 | May 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 24, 2022 | Dec 12, 2022 | — |
Fire prevention review Fire Department · SFFD | Oct 24, 2022 | Nov 28, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Oct 24, 2022 | May 10, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Apr 26, 2023 | Apr 26, 2023 | — |
Zoning review Planning · CP-ZOC | May 12, 2023 | May 12, 2023 | — |
Fire prevention review Fire Department · SFFD | May 12, 2023 | May 16, 2023 | — |
Fire prevention review Fire Department · SFFD | May 19, 2023 | May 23, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 23, 2023 | May 26, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $192,000
| Name | Role | License on permit |
|---|---|---|
| Chris Warner | Engineer | S4613 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026