335 Powell St
San Francisco permit 202209152520 · Tenderloin
Barrier removal to replace non-accessible rotating doors and side doors with two sets of automatic sliding doors (no public right away)
- Filed
- Sep 15, 2022
- Issued
- May 16, 2023 (8 months after filing)
- Completed
- Feb 28, 2024 (9 months after issuance)
For comparison, San Francisco permits with the same review (over-the-counter, with plans) filed in 2022 were typically issued within 1 month (median of 5,514 issued permits).
- Review stops
- 19 stops across 3 departments
- Comments issued
- Not recorded for this permit
- Put on hold
- Once
The city lists the review stops for this permit but not their results, so we can't tell whether reviewers asked for changes.
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 15, 2022 | Sep 15, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 15, 2022 | Sep 15, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 15, 2022 | Sep 15, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 15, 2022 | Sep 15, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 15, 2022 | Sep 15, 2022 | — |
Building plan review Building Inspection · BLDG | Sep 30, 2022 | Sep 30, 2022 | — |
Intake Building Inspection · INTAKE | Nov 3, 2022 | Nov 3, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 4, 2022 | Nov 4, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 4, 2022 | Nov 4, 2022 | — |
Structural plan approval Building Inspection · PAD-STR | Nov 4, 2022 | Nov 4, 2022 | — |
Intake Building Inspection · INTAKE | Nov 16, 2022 | Nov 16, 2022 | — |
Zoning review Planning · CP-ZOC | Nov 16, 2022 | Nov 16, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Nov 16, 2022 | Nov 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 16, 2022 | Nov 16, 2022 | — |
Fire prevention review Fire Department · SFFD | Nov 17, 2022 | Nov 17, 2022 | — |
Building plan review Building Inspection · BLDG | Nov 21, 2022 | Nov 21, 2022 | — |
Code enforcement Building Inspection · CES | Nov 21, 2022 | Nov 21, 2022 | — |
Building plan review Building Inspection · BLDG | May 16, 2023 | May 16, 2023 | — |
Central Permit Bureau Building Inspection · CPB | May 16, 2023 | May 16, 2023 | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- OTC alterations permit
- Status
- Complete
- Estimated cost
- $120,000
| Name | Role | License on permit |
|---|---|---|
| Michael John Stanton | Architect | C-11562 |
| Brendan D Dunnigan Hks Architects | Engineer | C28538 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2025