28 Sonoma St
San Francisco permit 202209202746 · North Beach
Interior remodel of entire bldg.all interior partitions & floors to be demolished & replaced with new structure.
- Filed
- Sep 20, 2022
- Issued
- Oct 4, 2023 (12 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 37 stops across 4 departments
- Comments issued
- 8 times, by Building Inspection
- Put on hold
- 5 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 20, 2022 | Sep 26, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 26, 2022 | Mar 28, 2023 | — |
Permit Processing Center Building Inspection · PPC | Sep 26, 2022 | Sep 25, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 8, 2023 | Feb 13, 2023 | — |
Zoning review Planning · CP-ZOC | Mar 28, 2023 | Mar 28, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 29, 2023 | Jun 20, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 29, 2023 | Sep 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 29, 2023 | Apr 25, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2023 | Jun 20, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 20, 2023 | Jul 19, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 19, 2023 | Jul 28, 2023 | — |
Building plan review Building Inspection · BLDG | Jul 28, 2023 | Aug 2, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 25, 2023 | Sep 25, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 25, 2023 | Aug 25, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 25, 2023 | Aug 31, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 25, 2023 | Oct 4, 2023 | Administrative |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 6, 2023 | Oct 17, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Oct 17, 2023 | Dec 22, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 17, 2023 | Nov 29, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Oct 17, 2023 | May 31, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 17, 2023 | Feb 26, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 17, 2023 | Jul 25, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Dec 21, 2023 | Dec 22, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 15, 2024 | Feb 15, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 22, 2024 | Mar 7, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 22, 2024 | Mar 18, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Mar 12, 2024 | Mar 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 29, 2024 | Apr 17, 2024 | Approved |
Building plan review Building Inspection · BLDG | Apr 10, 2024 | Apr 10, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | May 20, 2024 | May 20, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 3, 2024 | Jun 3, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Jun 3, 2024 | Jun 3, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jun 5, 2024 | Jun 14, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 5, 2024 | Jun 17, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jun 5, 2024 | Jul 16, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 5, 2024 | Jun 5, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 25, 2024 | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $615,000
| Name | Role | License on permit |
|---|---|---|
| Daniel Antonio Guich Studio Converge Architecture | Architect | C31614 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026