490 Avila St
San Francisco permit 202209212892 · Marina
Interior revised floor plans. updates to fixtures & finishes. updated lighting & power throughout. structural improvements to foundations at some locations. exterior work includes modifications to several windows & doors. replace windows in-kind at upper levels. infill (e) lightwell on east facade.
- Filed
- Sep 21, 2022
- Issued
- Nov 7, 2023 (14 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 20 stops across 4 departments
- Comments issued
- None
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 21, 2022 | Dec 2, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 2, 2022 | May 24, 2023 | — |
Permit Processing Center Building Inspection · PPC | Dec 2, 2022 | Oct 12, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | May 1, 2023 | May 1, 2023 | — |
Building plan review Building Inspection · BLDG | May 25, 2023 | Sep 13, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 25, 2023 | Aug 16, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 25, 2023 | May 31, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 25, 2023 | Jun 26, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Aug 16, 2023 | Aug 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | Sep 15, 2023 | Sep 19, 2023 | Administrative |
Street use and mapping Public Works · DPW-BSM | Sep 15, 2023 | Sep 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 15, 2023 | Sep 22, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 26, 2023 | Oct 2, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 2, 2023 | Oct 3, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 2, 2023 | Oct 3, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 2, 2023 | Oct 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 4, 2023 | Oct 4, 2023 | Approved |
Zoning review Planning · CP-ZOC | Oct 6, 2023 | Oct 10, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 6, 2023 | Oct 11, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 12, 2023 | Nov 7, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,523,500
| Name | Role | License on permit |
|---|---|---|
| Benjamin Clark Mcgriff Mcgriff Architects | Architect | C34047 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jun 2025