552 Jersey St
San Francisco permit 202209222993 · Noe Valley
Remodel of (e) duplex: add a new garage, kitchen and bathroom remodel, add new deck
- Filed
- Sep 22, 2022
- Issued
- Not issued yet
- Completed
- Not completed yet
- Review stops
- 24 stops across 5 departments
- Comments issued
- 3 times, by Planning, Building Inspection
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Intake Building Inspection · INTAKE | Sep 22, 2022 | Sep 22, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 5, 2022 | May 8, 2023 | Administrative |
Planning neighborhood notice Planning · CP-NP | May 9, 2023 | May 18, 2023 | Administrative |
Planning discretionary review Planning · CP-DR | Jun 29, 2023 | Dec 5, 2023 | Approved |
Permit Center Permit Center · PERMIT-CTR | Nov 13, 2023 | Apr 23, 2024 | — |
Intake Building Inspection · INTAKE | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Mar 7, 2024 | Mar 7, 2024 | Approved |
Building plan review Building Inspection · BLDG | Mar 7, 2024 | Mar 7, 2024 | Administrative |
Intake Building Inspection · INTAKE | Apr 17, 2024 | Apr 17, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Apr 17, 2024 | Apr 17, 2024 | Issued Comments |
Zoning review Planning · CP-ZOC | Apr 19, 2024 | Apr 19, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Sep 9, 2024 | Sep 27, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Sep 16, 2024 | Sep 16, 2024 | Not Applicable |
Building pre-screening Building Inspection · PRE-BLDG | Sep 18, 2024 | Sep 18, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 18, 2024 | Sep 18, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Sep 26, 2024 | Sep 26, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Sep 27, 2024 | Sep 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Sep 27, 2024 | In progress | In Progress |
Zoning review Planning · CP-ZOC | — | In progress | — |
Building plan review Building Inspection · BLDG | — | In progress | — |
Fire prevention review Fire Department · SFFD | — | In progress | — |
Public Utilities Commission review Public Utilities · SFPUC | — | In progress | — |
Permit Processing Center Building Inspection · PPC | — | In progress | — |
Central Permit Bureau Building Inspection · CPB | — | In progress | — |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Withdrawn
- Estimated cost
- $300,000
| Name | Role | License on permit |
|---|---|---|
| Cyrus Mashhoodi Cm Engineers | Engineer | C49394 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Dec 2024