35 Russia Av
San Francisco permit 202209233018 · Excelsior
Construction of 4 adu's to replace 8 (e) indoor parking spaces. (e) structure to remain. replace 4 garage doors with brick surfaced exterior wall with windows. construct storage loft above a section of new units. (n) electrical, plumbing & hvac. (n) cabinets, appliances, fixtures, & finishes.
- Filed
- Sep 23, 2022
- Issued
- Sep 13, 2024 (24 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 28 stops across 5 departments
- Comments issued
- None
- Put on hold
- 6 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Apartment and hotel inspection Building Inspection · HIS | Sep 23, 2022 | Sep 23, 2022 | — |
Central Permit Bureau Building Inspection · CPB | Sep 23, 2022 | Sep 28, 2022 | — |
Zoning review Planning · CP-ZOC | Sep 28, 2022 | Jul 26, 2023 | — |
Building plan review Building Inspection · BLDG | Sep 28, 2022 | Dec 28, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Sep 28, 2022 | Nov 3, 2022 | — |
Fire prevention review Fire Department · SFFD | Sep 28, 2022 | Dec 22, 2022 | — |
Street use and mapping Public Works · DPW-BSM | Sep 28, 2022 | Dec 29, 2022 | — |
Urban forestry Public Works · DPW-BUF | Sep 28, 2022 | Jan 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Sep 28, 2022 | Oct 5, 2022 | — |
Permit Processing Center Building Inspection · PPC | Sep 28, 2022 | Nov 27, 2023 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | Dec 22, 2022 | Dec 22, 2022 | — |
Mechanical and energy plan review Building Inspection · MECH | Dec 22, 2022 | Dec 27, 2022 | — |
Building plan review Building Inspection · BLDG | Mar 8, 2023 | Mar 9, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 8, 2023 | Mar 9, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 8, 2023 | Mar 8, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 8, 2023 | Mar 13, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 8, 2023 | Mar 14, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 8, 2023 | Mar 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 26, 2023 | Nov 22, 2023 | Administrative |
Building plan review Building Inspection · BLDG | Jul 27, 2023 | Jul 28, 2023 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Jul 27, 2023 | Jul 27, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Jul 27, 2023 | Jul 31, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Jul 27, 2023 | Jul 27, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Jul 27, 2023 | Jul 28, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 27, 2023 | Aug 1, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jul 28, 2023 | Jul 28, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Nov 22, 2023 | Nov 27, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2023 | Sep 13, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $510,606
| Name | Role | License on permit |
|---|---|---|
| Terryl Marshall Lofrano Lofrano Arch/Sculpture Design | Architect | C-7292 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025