San Francisco permit 202209233085 · Oceanview/Merced/Ingleside

ADUFull plan reviewIssued
Street view · Apr 2025
Google Street View of 1090 Randolph St, Apr 2025
Scope of work
As written on the permit application.

Obtain a cua (# 2022-009810) to merge (2) "in-law" units into one two-bedroom/one bath dwelling unit, and add religious use per cua. includes alterations & mep work. remove (e) bridge linking 1060 randolph to this property w/ all bridge supports removed. replace all windows in first floor unit.

Timeline
Key dates from the city record.
Filed
Sep 23, 2022
Issued
Aug 8, 2025 (34 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
50 stops across 4 departments
Comments issued
17 times, by Building Inspection, Public Works, Public Utilities
Put on hold
3 times
Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 5, 2022—

Zoning review

Planning · CP-ZOC

Nov 25, 2024Approved

Building plan review

Building Inspection · BLDG

Nov 3, 2022—

Mechanical and energy plan review

Building Inspection · MECH

Dec 20, 2024Issued Comments

Urban forestry

Public Works · DPW-BUF

Oct 22, 2022Issued Comments

Street use and mapping

Public Works · DPW-BSM

Oct 14, 2022—

Public Utilities Commission review

Public Utilities · SFPUC

Oct 18, 2022—

Permit Processing Center

Building Inspection · PPC

Jul 11, 2025Administrative

Zoning review

Planning · CP-ZOC

Jan 6, 2025Approved

Building plan review

Building Inspection · BLDG

Jan 9, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Dec 31, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Dec 23, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 30, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 15, 2025Administrative

Structural plan approval

Building Inspection · PAD-STR

Feb 24, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Feb 25, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Feb 19, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 26, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 19, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Feb 27, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Mar 4, 2025Issued Comments

Street use and mapping

Public Works · DPW-BSM

Apr 1, 2025Approved-Stipulated

Structural plan approval

Building Inspection · PAD-STR

Mar 21, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 28, 2025Issued Comments

Zoning review

Planning · CP-ZOC

Mar 24, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 31, 2025Issued Comments

Building plan review quality control

Building Inspection · BLDG-QC

Mar 31, 2025Approved

Zoning review

Planning · CP-ZOC

Apr 3, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Apr 4, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Apr 8, 2025Approved

Urban forestry

Public Works · DPW-BUF

Apr 11, 2025Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Apr 28, 2025Approved

Zoning review

Planning · CP-ZOC

May 14, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

May 6, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

May 19, 2025Approved

Street use and mapping

Public Works · DPW-BSM

May 19, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

May 28, 2025Approved

Urban forestry

Public Works · DPW-BUF

May 30, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Jun 9, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jun 10, 2025Approved

Zoning review

Planning · CP-ZOC

Jun 17, 2025Approved

Structural plan approval

Building Inspection · PAD-STR

Jun 10, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Jun 10, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jun 18, 2025Approved

Mechanical and energy plan review

Building Inspection · MECH

Jun 27, 2025Approved

Urban forestry

Public Works · DPW-BUF

Jul 7, 2025Issued Comments

Urban forestry

Public Works · DPW-BUF

Jul 7, 2025Approved

Development fee collection

Building Inspection · DFCU

Jul 10, 2025Administrative

Central Permit Bureau

Building Inspection · CPB

Aug 8, 2025Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Issued
Estimated cost
$284,558
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
David Scott Locicero

David Locicero

Authorized agent-othersC19452
Sources