3305 Jennings St
San Francisco permit 202209263119 · Bayview Hunters Point
(parcel a) - to construct a type v, 3-story, 2 dwelling units building. 6/03/2024: per dpw lot subdivision, add new addresses 3305, 3305a jennings street to new bldg #202209263119 wf
- Filed
- Sep 26, 2022
- Issued
- Jun 11, 2024 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 50 stops across 6 departments
- Comments issued
- 12 times, by Fire Department, Permit Center, Building Inspection, Public Works, Planning
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 26, 2022 | Oct 4, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2022 | Mar 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2022 | Jan 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 22, 2023 | Sep 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Mar 22, 2023 | Dec 13, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 22, 2023 | Dec 18, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2023 | Mar 29, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2023 | Apr 17, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 13, 2023 | Dec 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 15, 2023 | Jan 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 15, 2023 | Jan 22, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jan 4, 2024 | Jan 4, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jan 23, 2024 | Jan 23, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2024 | Jun 11, 2024 | Administrative |
Addendum 1: Arch mep structural final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2024 | Jul 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jul 19, 2024 | Jul 19, 2024 | Approved |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 22, 2024 | Jul 22, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 23, 2024 | Jul 23, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Oct 8, 2024 | Oct 21, 2024 | Issued Comments |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 16, 2024 | Oct 16, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 17, 2024 | Oct 17, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Dec 10, 2024 | Dec 27, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | Dec 19, 2024 | Dec 19, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Dec 24, 2024 | Dec 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 30, 2024 | Mar 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Mar 11, 2025 | Mar 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 11, 2025 | Mar 18, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Mar 11, 2025 | Mar 17, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 11, 2025 | Mar 12, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 11, 2025 | Apr 21, 2025 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 11, 2025 | Mar 17, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 11, 2025 | Mar 14, 2025 | Issued Comments |
Permit Processing Center Building Inspection · PPC | Mar 11, 2025 | Jan 2, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Mar 18, 2025 | Mar 18, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 21, 2025 | Apr 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Jun 25, 2025 | Jun 25, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jul 1, 2025 | Jul 2, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 8, 2025 | Aug 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 15, 2025 | Aug 18, 2025 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Aug 21, 2025 | Aug 21, 2025 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Aug 21, 2025 | Aug 21, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Sep 8, 2025 | Sep 8, 2025 | Approved |
Building plan review Building Inspection · BLDG | Sep 9, 2025 | Sep 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 9, 2025 | Sep 10, 2025 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Sep 21, 2025 | Oct 14, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 6, 2025 | Oct 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Oct 15, 2025 | Dec 22, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 15, 2025 | Oct 22, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2026 | Mar 2, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Kyle Tamar Brunel Pencil Box Architects | Architect | C35905 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011