3307 Jennings St
San Francisco permit 202209263120 · Bayview Hunters Point
(parcel b) - to construct a type v, 3-story, 2 dwelling units building.202209263120 6/03/2024: per dpw lot subdivision, add new addresses 3307, 3307a jennings street to new bldg #202209263120 wf
- Filed
- Sep 26, 2022
- Issued
- Jun 11, 2024 (20 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 59 stops across 6 departments
- Comments issued
- 16 times, by Fire Department, Permit Center, Building Inspection, Public Works
- Put on hold
- 4 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Sep 26, 2022 | Oct 4, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 4, 2022 | Mar 22, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 4, 2022 | Jan 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Mar 22, 2023 | Sep 15, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Mar 22, 2023 | Dec 13, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Mar 22, 2023 | Dec 15, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Mar 22, 2023 | Jan 22, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Mar 22, 2023 | Apr 17, 2023 | — |
Fire prevention review Fire Department · SFFD | Dec 13, 2023 | Dec 13, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 15, 2023 | Jan 4, 2024 | — |
Public Utilities Commission review Public Utilities · SFPUC | Dec 15, 2023 | Dec 27, 2023 | Approved |
Zoning review Planning · CP-ZOC | Jan 16, 2024 | Jan 16, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Jan 23, 2024 | Jan 23, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2024 | Jun 11, 2024 | Administrative |
Addendum 1: Arch structural mep final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Jul 15, 2024 | Jul 24, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Jul 22, 2024 | Jul 22, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Jul 23, 2024 | Jul 23, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Jul 24, 2024 | Jul 24, 2024 | Approved |
Permit Center Permit Center · PERMIT-CTR | Oct 8, 2024 | Oct 17, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Oct 11, 2024 | Oct 11, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Oct 16, 2024 | Oct 16, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 18, 2024 | Dec 31, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | Dec 31, 2024 | Dec 31, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 2, 2025 | Apr 11, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Apr 11, 2025 | May 8, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Apr 11, 2025 | May 8, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 11, 2025 | May 14, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Apr 11, 2025 | Apr 11, 2025 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 11, 2025 | Apr 16, 2025 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Apr 11, 2025 | May 14, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 11, 2025 | Apr 21, 2025 | Approved |
Zoning review Planning · CP-ZOC | Apr 11, 2025 | Apr 11, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Apr 11, 2025 | Apr 16, 2026 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | May 15, 2025 | May 15, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | May 16, 2025 | May 16, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 9, 2025 | Sep 9, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 26, 2025 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 10, 2025 | Sep 15, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 23, 2025 | Nov 3, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Oct 23, 2025 | Oct 29, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 30, 2025 | Dec 31, 2025 | Approved |
Building plan review Building Inspection · BLDG | Jan 2, 2026 | Jan 15, 2026 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 2, 2026 | Jan 15, 2026 | Administrative |
Urban forestry Public Works · DPW-BUF | Jan 2, 2026 | Jan 20, 2026 | Issued Comments |
Zoning review Planning · CP-ZOC | Jan 2, 2026 | Jan 5, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 5, 2026 | Jan 5, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Jan 12, 2026 | Jan 12, 2026 | Administrative |
Structural plan approval Building Inspection · PAD-STR | Jan 15, 2026 | Jan 15, 2026 | Administrative |
Building plan review Building Inspection · BLDG | Apr 2, 2026 | Apr 2, 2026 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Apr 2, 2026 | Apr 2, 2026 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Apr 3, 2026 | Apr 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 3, 2026 | Apr 9, 2026 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Apr 3, 2026 | Apr 15, 2026 | Approved |
Urban forestry Public Works · DPW-BUF | Apr 3, 2026 | Apr 3, 2026 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Apr 3, 2026 | Apr 7, 2026 | Approved |
Zoning review Planning · CP-ZOC | Apr 3, 2026 | Apr 3, 2026 | Approved |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 10, 2026 | Approved-Stipulated |
Fire prevention review Fire Department · SFFD | Apr 10, 2026 | Apr 13, 2026 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 16, 2026 | May 5, 2026 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Issued
- Estimated cost
- $750,000
| Name | Role | License on permit |
|---|---|---|
| Kyle Tamar Brunel Pencil Box Architects | Payor | C35905 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2011