585 Ortega St
San Francisco permit 202210053832 · Inner Sunset
Vertical and horizontal expansion. renovation and gut interior remodel of (e) 2-story, single family home. work includes 1 story vertical addition, partial expansion of front facade, and rear addition. (n) 3rd fl includes 2 (n) bedrooms and 2 (n) bathrooms, as well as (n) office space.
- Filed
- Oct 5, 2022
- Issued
- Sep 25, 2025 (36 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 33 stops across 5 departments
- Comments issued
- 10 times, by Building Inspection, Public Works
- Put on hold
- Once
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 5, 2022 | Oct 13, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 13, 2022 | Feb 7, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 13, 2022 | Sep 23, 2025 | Administrative |
Planning neighborhood notice Planning · CP-NP | Apr 7, 2023 | Feb 7, 2024 | — |
Building plan review Building Inspection · BLDG | Feb 7, 2024 | Mar 22, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Feb 7, 2024 | Mar 27, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Feb 7, 2024 | Feb 27, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2024 | Feb 8, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Mar 14, 2024 | Mar 21, 2024 | Issued Comments |
Building plan review quality control Building Inspection · BLDG-QC | Mar 21, 2024 | Mar 21, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 11, 2024 | Aug 1, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jul 12, 2024 | Jul 12, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 15, 2024 | Jul 15, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 3, 2024 | Sep 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 6, 2024 | Sep 6, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 6, 2024 | Sep 6, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Sep 10, 2024 | Oct 16, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Sep 10, 2024 | Oct 7, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 12, 2024 | Oct 1, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 13, 2024 | Sep 13, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 16, 2024 | Sep 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 16, 2024 | Sep 16, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Sep 27, 2024 | Sep 27, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 9, 2024 | Oct 11, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 11, 2024 | Oct 11, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Oct 15, 2024 | Oct 15, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Oct 16, 2024 | Oct 16, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Oct 17, 2024 | Oct 17, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 1, 2024 | Nov 8, 2024 | Approved |
Zoning review Planning · CP-ZOC | Nov 12, 2024 | Nov 18, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Nov 15, 2024 | Nov 15, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 3, 2024 | Sep 25, 2025 | Administrative |
Development fee collection Building Inspection · DFCU | Sep 23, 2025 | Sep 23, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $1,058,950
| Name | Role | License on permit |
|---|---|---|
| Martin C Kellogg Amlgm | Architect | C35171 |
| Michael Austin Hom Hom & Pisano Engineering Inc. | Engineer | 71450 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Aug 2015