56 A Williams Av
San Francisco permit 202210053837 · Bayview Hunters Point
To construct a type-vb, 2-story, adu structure.
- Filed
- Oct 5, 2022
- Issued
- Sep 28, 2023 (12 months after filing)
- Completed
- Jul 22, 2024 (10 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 30 stops across 5 departments
- Comments issued
- None
- Put on hold
- 9 times
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 5, 2022 | Oct 18, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 18, 2022 | Jun 20, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 18, 2022 | Apr 6, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Oct 18, 2022 | Mar 31, 2023 | — |
Fire prevention review Fire Department · SFFD | Oct 18, 2022 | Apr 14, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 18, 2022 | Oct 24, 2022 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 18, 2022 | Oct 19, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 18, 2022 | Aug 15, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | Mar 31, 2023 | Mar 31, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Mar 31, 2023 | Apr 13, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 31, 2023 | Apr 11, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 14, 2023 | Jun 12, 2023 | — |
Building plan review Building Inspection · BLDG | May 15, 2023 | May 22, 2023 | — |
Mechanical and energy plan review Building Inspection · MECH | May 15, 2023 | May 15, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | May 15, 2023 | Jun 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 15, 2023 | May 15, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 12, 2023 | Jun 26, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 12, 2023 | Aug 3, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jun 12, 2023 | Jun 13, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 12, 2023 | Jun 13, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jun 12, 2023 | Jun 22, 2023 | — |
Zoning review Planning · CP-ZOC | Jun 20, 2023 | Jul 5, 2023 | — |
Fire prevention review Fire Department · SFFD | Jun 26, 2023 | Aug 10, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 24, 2023 | Aug 4, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 24, 2023 | Jul 25, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 24, 2023 | Aug 3, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 10, 2023 | Aug 10, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 10, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Aug 15, 2023 | Aug 15, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Aug 15, 2023 | Sep 28, 2023 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- New construction wood frame
- Status
- Complete
- Estimated cost
- $270,368
| Name | Role | License on permit |
|---|---|---|
| Albert C Law | Architect | C38812 |
| Zhuren Lawrence Liao Lawrence Liao Str. Eng | Engineer | S3273 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2025