96 Caselli Av
San Francisco permit 202210134262 · Castro/Upper Market
Demolish (e) roof framing, rebuild gable roof 3'-6" higher, add a stair from second floor to new 3rd floor. add four sets of dormers and a roof deck at north. create 725 sf of new habitable floor area.
- Filed
- Oct 13, 2022
- Issued
- Oct 31, 2024 (25 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 43 stops across 6 departments
- Comments issued
- 12 times, by Building Inspection, Public Works, Public Utilities, Permit Center
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 13, 2022 | Oct 13, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 13, 2022 | Sep 7, 2023 | Approved |
Permit Processing Center Building Inspection · PPC | Oct 13, 2022 | Mar 20, 2024 | — |
Building plan review Building Inspection · BLDG | Sep 8, 2023 | Sep 29, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 8, 2023 | Sep 15, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Sep 8, 2023 | Sep 25, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Oct 20, 2023 | Dec 19, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 25, 2023 | Nov 14, 2023 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Oct 25, 2023 | Oct 30, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Oct 25, 2023 | Oct 26, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2023 | Dec 4, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 29, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2023 | Jan 22, 2024 | Approved-Stipulated |
Building plan review Building Inspection · BLDG | Dec 19, 2023 | Dec 19, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 28, 2023 | Jan 2, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 28, 2023 | Jan 2, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Jan 24, 2024 | Feb 6, 2024 | Approved-Stipulated |
Central Permit Bureau Building Inspection · CPB | Mar 20, 2024 | Oct 31, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Nov 19, 2024 | Dec 9, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | Dec 13, 2024 | Dec 27, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 27, 2024 | Dec 31, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Dec 31, 2024 | Jan 2, 2025 | Approved |
Building plan review Building Inspection · BLDG | Dec 31, 2024 | Feb 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Dec 31, 2024 | Feb 6, 2025 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Dec 31, 2024 | Mar 5, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Dec 31, 2024 | Jan 15, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Dec 31, 2024 | Jan 6, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Dec 31, 2024 | Mar 28, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 31, 2024 | Jan 7, 2025 | Approved |
Permit Processing Center Building Inspection · PPC | Dec 31, 2024 | Apr 3, 2025 | Administrative |
Mechanical plan review quality control Building Inspection · MECH-QC | Jan 24, 2025 | Jan 24, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Feb 3, 2025 | Feb 3, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 4, 2025 | Feb 4, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 5, 2025 | Feb 6, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Feb 6, 2025 | Feb 6, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Mar 3, 2025 | Mar 3, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Mar 4, 2025 | Mar 4, 2025 | Approved |
Zoning review Planning · CP-ZOC | Mar 13, 2025 | Mar 13, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Mar 13, 2025 | Mar 13, 2025 | Approved |
Building plan review Building Inspection · BLDG | Mar 17, 2025 | Mar 19, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Mar 17, 2025 | Mar 17, 2025 | Approved |
Building plan review quality control Building Inspection · BLDG-QC | Mar 19, 2025 | Mar 19, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Apr 3, 2025 | In progress | In Progress |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Cancelled
- Estimated cost
- $296,000
| Name | Role | License on permit |
|---|---|---|
| Brent Caldbick Martin Martin Partners | Architect | C35603 |
| Gregory Paul Wallace Gregory Paul Wallace Struct | Engineer | S3308 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Sep 2026