96 Caselli Av

San Francisco permit 202210134262 · Castro/Upper Market

AdditionFull plan reviewCancelled
Street view · Sep 2026
Google Street View of 96 Caselli Av, Sep 2026
Scope of work
As written on the permit application.

Demolish (e) roof framing, rebuild gable roof 3'-6" higher, add a stair from second floor to new 3rd floor. add four sets of dormers and a roof deck at north. create 725 sf of new habitable floor area.

Timeline
Key dates from the city record.
Filed
Oct 13, 2022
Issued
Oct 31, 2024 (25 months after filing)
Completed
Not completed yet

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
43 stops across 6 departments
Comments issued
12 times, by Building Inspection, Public Works, Public Utilities, Permit Center

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 13, 2022—

Zoning review

Planning · CP-ZOC

Sep 7, 2023Approved

Permit Processing Center

Building Inspection · PPC

Mar 20, 2024—

Building plan review

Building Inspection · BLDG

Sep 29, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Sep 15, 2023Issued Comments

Public Utilities Commission review

Public Utilities · SFPUC

Sep 25, 2023Issued Comments

Building plan review

Building Inspection · BLDG

Dec 19, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Nov 14, 2023Approved-Stipulated

Public Utilities Commission review

Public Utilities · SFPUC

Oct 30, 2023Issued Comments

Zoning review

Planning · CP-ZOC

Oct 26, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Dec 4, 2023Approved

Zoning review

Planning · CP-ZOC

Nov 29, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Jan 22, 2024Approved-Stipulated

Building plan review

Building Inspection · BLDG

Dec 19, 2023Approved

Zoning review

Planning · CP-ZOC

Jan 2, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 2, 2024Approved

Urban forestry

Public Works · DPW-BUF

Feb 6, 2024Approved-Stipulated

Central Permit Bureau

Building Inspection · CPB

Oct 31, 2024Administrative

Addendum 1: Final plans

Review stopFinishedResult

Permit Center

Permit Center · PERMIT-CTR

Dec 9, 2024Issued Comments

Permit Center

Permit Center · PERMIT-CTR

Dec 27, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Dec 31, 2024Administrative

Zoning review

Planning · CP-ZOC

Jan 2, 2025Approved

Building plan review

Building Inspection · BLDG

Feb 6, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Feb 6, 2025Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Mar 5, 2025Approved

Fire prevention review

Fire Department · SFFD

Jan 15, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Jan 6, 2025Approved

Urban forestry

Public Works · DPW-BUF

Mar 28, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Jan 7, 2025Approved

Permit Processing Center

Building Inspection · PPC

Apr 3, 2025Administrative

Mechanical plan review quality control

Building Inspection · MECH-QC

Jan 24, 2025Administrative

Building plan review

Building Inspection · BLDG

Feb 3, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 4, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 6, 2025Issued Comments

Building plan review

Building Inspection · BLDG

Feb 6, 2025Issued Comments

Structural plan approval

Building Inspection · PAD-STR

Mar 3, 2025Approved

Public Utilities Commission review

Public Utilities · SFPUC

Mar 4, 2025Approved

Zoning review

Planning · CP-ZOC

Mar 13, 2025Approved

Street use and mapping

Public Works · DPW-BSM

Mar 13, 2025Approved

Building plan review

Building Inspection · BLDG

Mar 19, 2025Approved

Fire prevention review

Fire Department · SFFD

Mar 17, 2025Approved

Building plan review quality control

Building Inspection · BLDG-QC

Mar 19, 2025Approved

Central Permit Bureau

Building Inspection · CPB

In progressIn Progress

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Cancelled
Estimated cost
$296,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Brent Caldbick Martin

Martin Partners

ArchitectC35603
Gregory Paul Wallace

Gregory Paul Wallace Struct

EngineerS3308
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202210134262 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record