212 Genebern Wy
San Francisco permit 202210174502 · Bernal Heights
Renovation of (e) home. on main level, enlarged kitchen to include bar seating and open walls to family and dining rooms. attached bath added to 2 bedrooms, and maintain 1 bedroom and full bath. new direct vent fireplace in living room. on lower level adding: staircase from main level, (n)laundry,
- Filed
- Oct 17, 2022
- Issued
- Mar 15, 2024 (17 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 56 stops across 5 departments
- Comments issued
- 13 times, by Building Inspection, Public Utilities, Permit Center, Public Works
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 14, 2022 | Oct 21, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2022 | Aug 28, 2023 | Approved |
Building plan review Building Inspection · BLDG | Oct 21, 2022 | Aug 2, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Oct 21, 2022 | Jun 1, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Oct 21, 2022 | May 18, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Oct 21, 2022 | Oct 24, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2022 | Feb 29, 2024 | Administrative |
Public Utilities Commission review Public Utilities · SFPUC | May 16, 2023 | Jun 2, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 25, 2023 | Jun 1, 2023 | — |
Urban forestry Public Works · DPW-BUF | Jun 1, 2023 | Jun 1, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jun 16, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 16, 2023 | Jun 22, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jul 21, 2023 | Jul 24, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Jul 21, 2023 | Jul 28, 2023 | Issued Comments |
Urban forestry Public Works · DPW-BUF | Aug 2, 2023 | Aug 2, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 3, 2023 | Aug 3, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 10, 2023 | Aug 10, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 15, 2023 | Aug 16, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Aug 22, 2023 | Aug 29, 2023 | Approved |
Urban forestry Public Works · DPW-BUF | Aug 22, 2023 | Jan 16, 2024 | Approved-Stipulated |
Public Utilities Commission review Public Utilities · SFPUC | Aug 22, 2023 | Aug 24, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 6, 2023 | Dec 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Dec 6, 2023 | Jan 3, 2024 | Administrative |
Street use and mapping Public Works · DPW-BSM | Dec 6, 2023 | Dec 27, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Dec 6, 2023 | Dec 8, 2023 | Approved |
Zoning review Planning · CP-ZOC | Dec 12, 2023 | Dec 12, 2023 | Approved |
Building plan review Building Inspection · BLDG | Jan 16, 2024 | Jan 16, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jan 18, 2024 | Feb 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 18, 2024 | Jan 30, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jan 18, 2024 | Feb 27, 2024 | Approved |
Development fee collection Building Inspection · DFCU | Feb 29, 2024 | Feb 29, 2024 | Administrative |
Central Permit Bureau Building Inspection · CPB | Feb 29, 2024 | Mar 15, 2024 | Administrative |
Addendum 1: Final plans
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Apr 5, 2024 | Apr 12, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Apr 10, 2024 | Apr 10, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 10, 2024 | Apr 10, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 12, 2024 | Apr 12, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 7, 2024 | May 21, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 16, 2024 | May 16, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 21, 2024 | May 21, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 22, 2024 | May 22, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 24, 2024 | Jun 12, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 24, 2024 | Jun 3, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 24, 2024 | Jun 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 24, 2024 | Jun 6, 2024 | Issued Comments |
Permit Processing Center Building Inspection · PPC | May 24, 2024 | Nov 27, 2024 | Administrative |
Urban forestry Public Works · DPW-BUF | Jun 26, 2024 | Jul 2, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 26, 2024 | Jun 26, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 6, 2024 | Sep 6, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 17, 2024 | Sep 17, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Oct 29, 2024 | Oct 29, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 4, 2024 | Nov 4, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 4, 2024 | Nov 4, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 6, 2024 | Nov 6, 2024 | Approved |
Urban forestry Public Works · DPW-BUF | Nov 19, 2024 | Nov 19, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 19, 2024 | Nov 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Nov 27, 2024 | Dec 9, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $961,808
| Name | Role | License on permit |
|---|---|---|
| Ethan C Andersen Drafting Cafe Architects | Architect | C34235 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Jan 2023