As written on the permit application.

Vertical addition at the (e) second level roof terrace, enclosure of (e) 1st level porch. addition of 1 bedroom and 1 bathroom. remodel of existing bathrooms and an office.

Timeline
Key dates from the city record.
Filed
Oct 18, 2022
Issued
Oct 3, 2023 (11 months after filing)
Completed
Jun 10, 2025 (20 months after issuance)

For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).

City plan review
Each review stop the plans went through, from the city's routing record.
Review stops
30 stops across 5 departments
Comments issued
4 times, by Fire Department, Building Inspection
Put on hold
Once

Main permit

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Oct 18, 2022—

Zoning review

Planning · CP-ZOC

Jun 12, 2023—

Permit Processing Center

Building Inspection · PPC

Sep 19, 2023—

Building plan review

Building Inspection · BLDG

Dec 23, 2022—

Building plan review

Building Inspection · BLDG

Mar 31, 2023—

Planning neighborhood notice

Planning · CP-NP

Jun 12, 2023—

Building plan review

Building Inspection · BLDG

Mar 8, 2023—

Fire prevention review

Fire Department · SFFD

Aug 31, 2023Issued Comments

Street use and mapping

Public Works · DPW-BSM

Jun 27, 2023—

Public Utilities Commission review

Public Utilities · SFPUC

Jul 18, 2023Approved

Fire prevention review

Fire Department · SFFD

Sep 6, 2023Approved

Street use and mapping

Public Works · DPW-BSM

Sep 14, 2023Approved

Central Permit Bureau

Building Inspection · CPB

Oct 3, 2023Administrative

Addendum 1: Arch structural mep t24 final

Review stopFinishedResult

Central Permit Bureau

Building Inspection · CPB

Nov 6, 2023Administrative

Permit Processing Center

Building Inspection · PPC

Mar 8, 2024—

Building plan review

Building Inspection · BLDG

Jan 5, 2024Issued Comments

Mechanical and energy plan review

Building Inspection · MECH

Jan 2, 2024Issued Comments

Fire prevention review

Fire Department · SFFD

Feb 22, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Nov 7, 2023Approved

Public Utilities Commission review

Public Utilities · SFPUC

Nov 16, 2023Approved

Building plan review

Building Inspection · BLDG

Feb 21, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Feb 23, 2024Issued Comments

Street use and mapping

Public Works · DPW-BSM

Feb 27, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 20, 2024Approved

Mechanical and energy plan review

Building Inspection · MECH

Mar 4, 2024Approved

Building plan review

Building Inspection · BLDG

Mar 1, 2024Approved

Fire prevention review

Fire Department · SFFD

Mar 5, 2024Approved

Street use and mapping

Public Works · DPW-BSM

Mar 4, 2024Approved

Public Utilities Commission review

Public Utilities · SFPUC

Feb 29, 2024Approved

Central Permit Bureau

Building Inspection · CPB

Mar 11, 2024Administrative

Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.

Permit details
Permit type
Additions alterations or repairs
Status
Complete
Estimated cost
$132,000
People named on this permit
Only people we matched to a California license are listed.
NameRoleLicense on permit
Geddes J Ulinskas

Geddes Ulinskas Arch.

ArchitectC27862
Brendan Forslund Beazley

Jon Brody Structural Engineers

EngineerS5660
Sources
Everything on this page comes from public records. Check them yourself.
Permit 202210184534 on the city's permit tracking site

San Francisco Department of Building Inspection, the official record