376 Prospect Av
San Francisco permit 202210184537 · Bernal Heights
Comply w/ nov #202062071,202056562,202056561: #378 3/f-relocate exterior access stairs to side yard. #376 2/f-add half-bath at rear. g/f legalize (n) j-adu (487 sf). remove (e) non-code compliant 2/f kitchen & deck. extend g/f into crawl space. leveled floor for (n) living/ dining room & (n) bath.
- Filed
- Oct 18, 2022
- Issued
- Nov 13, 2023 (13 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 42 stops across 5 departments
- Comments issued
- 7 times, by Public Works, Building Inspection
- Put on hold
- 3 times
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2022 | Oct 28, 2022 | — |
Code enforcement Building Inspection · CES | Oct 19, 2022 | Oct 19, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 28, 2022 | Mar 1, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 28, 2022 | Sep 19, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Dec 28, 2022 | Mar 1, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 3, 2023 | Mar 30, 2023 | — |
Urban forestry Public Works · DPW-BUF | Mar 3, 2023 | May 23, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 3, 2023 | Mar 9, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 3, 2023 | Apr 12, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 3, 2023 | Mar 23, 2023 | — |
Fire prevention review Fire Department · SFFD | Apr 12, 2023 | Apr 12, 2023 | — |
Zoning review Planning · CP-ZOC | Apr 17, 2023 | Apr 17, 2023 | — |
Zoning review Planning · CP-ZOC | May 23, 2023 | May 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | May 23, 2023 | Aug 21, 2023 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | May 23, 2023 | Aug 2, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2023 | Jun 2, 2023 | — |
Urban forestry Public Works · DPW-BUF | Aug 14, 2023 | Aug 22, 2023 | Approved |
Zoning review Planning · CP-ZOC | Aug 14, 2023 | Aug 14, 2023 | Approved |
Building plan review Building Inspection · BLDG | Aug 14, 2023 | Sep 13, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Aug 14, 2023 | Aug 15, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Aug 14, 2023 | Aug 15, 2023 | Approved |
Development fee collection Building Inspection · DFCU | Sep 14, 2023 | Sep 14, 2023 | Administrative |
Central Permit Bureau Building Inspection · CPB | Sep 19, 2023 | Nov 13, 2023 | Administrative |
Addendum 1: Final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Jan 4, 2024 | Jan 9, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Jan 9, 2024 | Jan 25, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jan 9, 2024 | Feb 16, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jan 9, 2024 | Jan 31, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 9, 2024 | Jan 30, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jan 9, 2024 | Jan 10, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | Jan 9, 2024 | Jul 30, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | Feb 16, 2024 | Feb 16, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Apr 14, 2024 | Apr 29, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | May 14, 2024 | Jun 3, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | Jun 10, 2024 | Jun 10, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jul 16, 2024 | Jul 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 16, 2024 | Jul 23, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Jul 16, 2024 | Jul 29, 2024 | Approved |
Fire prevention review Fire Department · SFFD | Jul 16, 2024 | Jul 18, 2024 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Jul 16, 2024 | Jul 17, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 18, 2024 | Jul 18, 2024 | Approved |
Zoning review Planning · CP-ZOC | Jul 30, 2024 | Jul 30, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jul 30, 2024 | Aug 28, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $150,000
| Name | Role | License on permit |
|---|---|---|
| Winnie Hing-Wan Tam Winnie Tam | Architect | C31166 |
| Stephen Chan | Engineer | 4533 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Feb 2025