2442 Great Hy
San Francisco permit 202210184580 · Sunset/Parkside
Addition of a new penthouse stair & private roof deck @ unit #3 to an existing 3 story 4 unit apartment.
- Filed
- Oct 18, 2022
- Issued
- Jan 24, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 17 stops across 5 departments
- Comments issued
- Twice, by Building Inspection, Fire Department
- Put on hold
- Twice
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2022 | Oct 21, 2022 | — |
Zoning review Planning · CP-ZOC | Oct 21, 2022 | Mar 30, 2023 | — |
Permit Processing Center Building Inspection · PPC | Oct 21, 2022 | Dec 13, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Feb 6, 2023 | Mar 27, 2023 | — |
Building plan review Building Inspection · BLDG | Mar 30, 2023 | Sep 20, 2023 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Mar 30, 2023 | Apr 28, 2023 | — |
Fire prevention review Fire Department · SFFD | Mar 30, 2023 | Nov 20, 2023 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Mar 30, 2023 | Apr 5, 2023 | — |
Public Utilities Commission review Public Utilities · SFPUC | Mar 30, 2023 | May 5, 2023 | — |
Building plan review Building Inspection · BLDG | Oct 27, 2023 | Nov 7, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 28, 2023 | Nov 30, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 28, 2023 | Nov 30, 2023 | Approved |
Building plan review Building Inspection · BLDG | Nov 28, 2023 | Dec 6, 2023 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Nov 28, 2023 | Nov 29, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 28, 2023 | Nov 29, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 28, 2023 | Dec 1, 2023 | Approved |
Central Permit Bureau Building Inspection · CPB | Dec 13, 2023 | Jan 24, 2024 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $145,760
| Name | Role | License on permit |
|---|---|---|
| Eric M Dumican Dumican Mosey Architects | Architect | C31398 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken May 2022