15 Walnut St
San Francisco permit 202210184608 · Presidio Heights
Restoration of an existing archur brown bldg.; expansion of west facade on all levels, expansion od south facade on level 2, interior remodel at all levels; (n) vertical circulation; (n) north facade design; full seismic upgrade; landscaping work include excavation to lower southwest garden,
- Filed
- Oct 18, 2022
- Issued
- Jan 30, 2024 (15 months after filing)
- Completed
- Not completed yet
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 68 stops across 7 departments
- Comments issued
- 21 times, by Building Inspection, Fire Department, Public Health, Permit Center, Public Works
- Put on hold
- Twice
Main permit
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 18, 2022 | Oct 31, 2022 | — |
Permit Processing Center Building Inspection · PPC | Oct 31, 2022 | Jan 23, 2024 | Administrative |
Zoning review Planning · CP-ZOC | Nov 1, 2022 | Jun 22, 2023 | — |
Public health review Public Health · HEALTH | Jan 20, 2023 | May 22, 2023 | — |
Planning neighborhood notice Planning · CP-NP | Apr 20, 2023 | May 5, 2023 | — |
Building plan review Building Inspection · BLDG | Jun 23, 2023 | Aug 4, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 23, 2023 | Sep 1, 2023 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 23, 2023 | Jul 24, 2023 | — |
Street use and mapping Public Works · DPW-BSM | Jun 23, 2023 | Jul 5, 2023 | — |
Zoning review Planning · CP-ZOC | Jul 6, 2023 | Jul 7, 2023 | — |
Public health review Public Health · HEALTH | Jul 26, 2023 | Sep 11, 2023 | Issued Comments |
Fire prevention review Fire Department · SFFD | Sep 8, 2023 | Sep 8, 2023 | Approved |
Building plan review Building Inspection · BLDG | Sep 14, 2023 | Sep 26, 2023 | Issued Comments |
Zoning review Planning · CP-ZOC | Sep 14, 2023 | Sep 20, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 14, 2023 | Sep 22, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Sep 14, 2023 | Sep 21, 2023 | Approved |
Public health review Public Health · HEALTH | Sep 19, 2023 | Sep 19, 2023 | Issued Comments |
Building plan review Building Inspection · BLDG | Nov 20, 2023 | Nov 29, 2023 | Approved |
Zoning review Planning · CP-ZOC | Nov 20, 2023 | Nov 30, 2023 | Approved |
Fire prevention review Fire Department · SFFD | Nov 20, 2023 | Nov 20, 2023 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Nov 20, 2023 | Nov 30, 2023 | Approved |
Street use and mapping Public Works · DPW-BSM | Nov 20, 2023 | Jan 12, 2024 | Approved-Stipulated |
Public health review Public Health · HEALTH | Dec 4, 2023 | Dec 6, 2023 | Approved-Stipulated |
Street use and mapping Public Works · DPW-BSM | Jan 17, 2024 | Jan 17, 2024 | Approved-Stipulated |
Urban forestry Public Works · DPW-BUF | Jan 17, 2024 | Jan 19, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jan 23, 2024 | Jan 30, 2024 | Administrative |
Addendum 1: Arch structural mep final
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Permit Center Permit Center · PERMIT-CTR | Mar 29, 2024 | Apr 8, 2024 | Issued Comments |
Electrical pre-screening Building Inspection · PRE-MECH-E | Apr 2, 2024 | Apr 2, 2024 | Not Applicable |
Mechanical pre-screening Building Inspection · PRE-MECH | Apr 3, 2024 | Apr 3, 2024 | Issued Comments |
Building pre-screening Building Inspection · PRE-BLDG | Apr 8, 2024 | Apr 8, 2024 | Issued Comments |
Permit Center Permit Center · PERMIT-CTR | May 9, 2024 | May 22, 2024 | Approved |
Building pre-screening Building Inspection · PRE-BLDG | May 22, 2024 | May 22, 2024 | Approved |
Mechanical pre-screening Building Inspection · PRE-MECH | May 22, 2024 | May 22, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | May 23, 2024 | May 23, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 23, 2024 | Jul 11, 2024 | Administrative |
Building plan review Building Inspection · BLDG | May 23, 2024 | Jul 22, 2024 | Administrative |
Mechanical and energy plan review Building Inspection · MECH | May 23, 2024 | Jun 25, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | May 23, 2024 | Jul 5, 2024 | Approved |
Street use and mapping Public Works · DPW-BSM | May 23, 2024 | Jun 24, 2024 | Issued Comments |
Urban forestry Public Works · DPW-BUF | May 23, 2024 | Sep 4, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | May 23, 2024 | Jun 6, 2024 | Approved |
Public health review Public Health · HEALTH | May 23, 2024 | May 28, 2024 | Approved |
Permit Processing Center Building Inspection · PPC | May 23, 2024 | Mar 13, 2025 | Administrative |
Zoning review Planning · CP-ZOC | May 29, 2024 | May 29, 2024 | Approved |
Building plan review Building Inspection · BLDG | Jul 22, 2024 | Aug 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jul 22, 2024 | Aug 8, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Sep 25, 2024 | Sep 25, 2024 | Approved |
Building plan review Building Inspection · BLDG | Sep 27, 2024 | Oct 2, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Oct 9, 2024 | Dec 19, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Oct 9, 2024 | Oct 9, 2024 | Issued Comments |
Mechanical plan review quality control Building Inspection · MECH-QC | Oct 10, 2024 | Oct 10, 2024 | Administrative |
Building plan review Building Inspection · BLDG | Nov 12, 2024 | Nov 20, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Nov 21, 2024 | Nov 21, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Dec 9, 2024 | Dec 17, 2024 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Dec 18, 2024 | Dec 18, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 7, 2025 | Jan 16, 2025 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Jan 17, 2025 | Jan 17, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Jan 29, 2025 | Jan 31, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2025 | Jan 30, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Jan 30, 2025 | Jan 30, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Feb 4, 2025 | Feb 4, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Feb 5, 2025 | Feb 5, 2025 | Approved |
Urban forestry Public Works · DPW-BUF | Feb 7, 2025 | Mar 11, 2025 | Approved |
Zoning review Planning · CP-ZOC | Feb 7, 2025 | Feb 10, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Feb 7, 2025 | Feb 7, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Feb 7, 2025 | Feb 10, 2025 | Approved |
Public health review Public Health · HEALTH | Feb 7, 2025 | Feb 7, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Mar 13, 2025 | Mar 24, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Issued
- Estimated cost
- $3,750,000
| Name | Role | License on permit |
|---|---|---|
| Andrew Skurman Andrew Skurman Arch. | Architect | C23797 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Apr 2022