3912 24th St
San Francisco permit 202210204833 · Noe Valley
Addition at the 4th flr addition to an existing three story mix use containing one commerical unit occupying the first flr and basement and two resd unit. adding second story to the third floor residental unit at fourth flr. creating a two story residential unit with a private roof deck.
- Filed
- Oct 20, 2022
- Issued
- Oct 10, 2025 (36 months after filing)
- Completed
- Aug 31, 2026 (11 months after issuance)
For comparison, San Francisco permits with the same review (full plan review) filed in 2022 typically took 12 months to be issued (median of 872 issued permits).
- Review stops
- 22 stops across 5 departments
- Comments issued
- 9 times, by Building Inspection, Fire Department, Public Works
| Review stop | Arrived | Finished | Result |
|---|---|---|---|
Central Permit Bureau Building Inspection · CPB | Oct 20, 2022 | Dec 6, 2022 | — |
Zoning review Planning · CP-ZOC | Dec 6, 2022 | Jun 24, 2024 | Approved |
Central Permit Bureau Building Inspection · CPB | Jun 17, 2024 | Jun 17, 2024 | Administrative |
Permit Processing Center Building Inspection · PPC | Jun 17, 2024 | Oct 6, 2025 | Administrative |
Building plan review Building Inspection · BLDG | Jun 25, 2024 | Aug 2, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Jun 25, 2024 | Jul 18, 2024 | Issued Comments |
Fire prevention review Fire Department · SFFD | Jun 25, 2024 | Aug 12, 2024 | Issued Comments |
Street use and mapping Public Works · DPW-BSM | Jun 25, 2024 | Jun 26, 2024 | Issued Comments |
Public Utilities Commission review Public Utilities · SFPUC | Jun 25, 2024 | Jul 17, 2024 | Approved |
Structural plan approval Building Inspection · PAD-STR | Jul 25, 2024 | Jul 30, 2024 | Issued Comments |
Mechanical and energy plan review Building Inspection · MECH | Aug 1, 2024 | Aug 1, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Sep 4, 2024 | Sep 4, 2024 | Issued Comments |
Structural plan approval Building Inspection · PAD-STR | Sep 5, 2024 | Sep 5, 2024 | Issued Comments |
Building plan review Building Inspection · BLDG | Jul 17, 2025 | Aug 8, 2025 | Issued Comments |
Building plan review Building Inspection · BLDG | Aug 26, 2025 | Sep 25, 2025 | Approved |
Structural plan approval Building Inspection · PAD-STR | Aug 26, 2025 | Aug 27, 2025 | Approved |
Mechanical and energy plan review Building Inspection · MECH | Sep 9, 2025 | Sep 9, 2025 | Approved |
Fire prevention review Fire Department · SFFD | Sep 11, 2025 | Sep 11, 2025 | Approved |
Street use and mapping Public Works · DPW-BSM | Sep 12, 2025 | Sep 12, 2025 | Approved |
Zoning review Planning · CP-ZOC | Oct 3, 2025 | Oct 6, 2025 | Approved |
Public Utilities Commission review Public Utilities · SFPUC | Oct 3, 2025 | Oct 6, 2025 | Approved |
Central Permit Bureau Building Inspection · CPB | Oct 6, 2025 | Oct 10, 2025 | Administrative |
Source: DataSF 87xy-gk8d (Building Permit Addenda with Routing), retrieved Nov 6, 2026. Reviewer names and notes are left out.
- Permit type
- Additions alterations or repairs
- Status
- Complete
- Estimated cost
- $319,000
| Name | Role | License on permit |
|---|---|---|
| Leonardo L Zylberberg Leonardozylberberg Architect | Architect | C27342 |
| Albert Urrutia Atrium Structural Engineers | Engineer | S2994 |
San Francisco Department of Building Inspection, the official record
- DataSF Building PermitsAddress, scope, cost, dates and statusRetrieved Nov 5, 2026
- DataSF Building Permit ContactsArchitects and engineers named on the permitRetrieved Nov 5, 2026
- DataSF Building Permit Addenda with RoutingPlan review stops and resultsRetrieved Nov 6, 2026
- Google Street ViewStreet photoTaken Mar 2021